Sterling sse manual Mounting on the processing machine, Mounting onto a machine hopper

Page 25

Machine-Side Hopper Loaders

4.4.1. Mounting on the processing machine

A VT Series adapter is required to mount the loader on the processing machine. Two-liter models require a VT 1.0 adapter. Five-liter models require a VT 2.3/70 or VT 2.8/70 adapter. Use the following procedure to mount the loader to the processing machine:

1.

Mount the VT Series adapter onto the flange

 

 

of the processing machine.

Figure 5: VT Adapter

 

 

2.

Mount the loader onto the adapter.

 

FObserve the bearing capacity of the machine flange.

4.4.2. Mounting onto a machine hopper

Two-liter models require an EF 190 welding flange for mounting onto a machine hopper. Five-liter models can be mounted to a machine hopper using either the EF 253 welding flange or the MF 253 assembly flange.

Using the EF Series Welding Flange:

LPlease observe all safety regulations for the operation of welding equipments.

Always wear safety goggles.

Figure 6: EF Welding Flange

1.Weld the welding flange into the machine hopper lid.

2.Mount the loader onto the welding flange.

Using the MF Series Assembly Flange (Five liter models only)

1.

Mount the assembly flange into the machine hopper lid.

 

2.

Mount the loader onto the assembly flange.

 

Figure 7: MF Assembly Flange

 

 

 

 

 

4-6 Assembly instructions

Image 25
Contents Operating Instructions Machine-Side Hopper Loader SSE Series Machine-Side Hopper Loaders Iii Machine-Side Hopper Loaders Parts and Service Department Table of Contents Accessories 11-1 Electrical manual 12-1 General instructions Machine-Side Hopper Loaders Legal basis Explanations and informationFields of applications Page Safety instructions General For your safetyAssembly Operation MaintenanceFor the operating safety of the equipment Page Transport, assembly and storage Transport and packing AssemblyStorage Assembly instructions Liter model UnpackingDump valve and sensor Installing the dump valve sensorAttaching the pickup wand Mounting MountingMounting onto a machine hopper Mounting on the processing machineMounting onto DT 30 dosing station Mounting onto mixing hoppers with lateral inletCompressed air connection Electrical connectionX7, ZKW Installation of the optional proportioning valveConnecting Material Lines Functional description Controller Sequence of operationOperation Checking the flexible hose Switching on the unitSetting the conveying time Setting the purge time optional Initial operation Switching off the unitPage Troubleshooting Alarms Maintenance Machine-Side Hopper Loaders Maintenance intervals Changing the sealing ring of the outlet flap Servicing the loaderAdjusting the dump valve sensor Cleaning the unit Order numbers Filter cloth Wire cloth Replacing carbon brushes at the motor InstallationMachine-Side Hopper Loaders Disposal Instructions Taking out of service, dismantling, disposalTechnical data Specifications Liter model Brushless motor Loader Capacity Dimension Sheet Liter model Liter brushless model Spare parts list Parts breakdown, brush-type motor 10.2.1 V, 50 Hz Parts lists, 2-liter model10.2.2 V, 60 Hz 10.2.4 V, 60 Hz with active cleaning 10.2.3 V, 50 Hz with active cleaning10.3.1 V, 50 Hz V66372 Parts list, 5-liter modelPos. Order no. Designation 10.3.2 V, 60 Hz V66378US10.3.4 V, 60 Hz with active cleaning 10.3.3 V, 50 Hz with active cleaningParts breakdown and list, 5-liter model with brushless motor 10.5 V, 50 Hz Accessories Page Electrical manual Page Page Page Page Page Page Page Page Page Quick Start Guide Setting the loader convey time