Machine-Side Hopper Loaders

3.1. Transport and packing

MPlease ensure adequate carrying capacity of the lifting equipment.

The equipment passes rigorous testing in the factory and is packed carefully to avoid transport damage.

Please check packing on delivery for transport damage.

The inlet and discharge flanges are sealed with plugs, so that no dirt can enter during transport. Plugs must be removed before assembly.

Packing materials should be disposed of according to environmental laws or reused.

Only use for transport of the equipment a suitable lifting device (e. g. a fork lift truck or a workshop crane).

Transport must be shock-proofed and free from vibrations.

3.2. Assembly

MPlease ensure adequate carrying capacity of the lifting equipment.

Check the carrying capacity of the point of installation, particularly if installed on a platform.

The place selected for installation should be as free of vibrations as possible. The main power switch must be freely accessible.

Ground the equipment against electrostatic charging.

3.3. Storage

The control system may only be stored at temperatures from -13 to +131 °F (-25 to +55°C).

Between delivery and machine commissioning, the equipment should be stored in a dry, dust-free and vibration-free room.

3-2 Transport, assembly and storage

Image 19
Contents Operating Instructions Machine-Side Hopper Loader SSE Series Machine-Side Hopper Loaders Iii Machine-Side Hopper Loaders Parts and Service Department Table of Contents Accessories 11-1 Electrical manual 12-1 General instructions Machine-Side Hopper Loaders Legal basis Explanations and informationFields of applications Page Safety instructions General For your safetyAssembly Operation MaintenanceFor the operating safety of the equipment Page Transport, assembly and storage Transport and packing AssemblyStorage Assembly instructions Liter model UnpackingDump valve and sensor Installing the dump valve sensorAttaching the pickup wand Mounting MountingMounting onto a machine hopper Mounting on the processing machineMounting onto DT 30 dosing station Mounting onto mixing hoppers with lateral inletCompressed air connection Electrical connectionX7, ZKW Installation of the optional proportioning valveConnecting Material Lines Functional description Controller Sequence of operationOperation Checking the flexible hose Switching on the unitSetting the conveying time Setting the purge time optional Initial operation Switching off the unitPage Troubleshooting Alarms Maintenance Machine-Side Hopper Loaders Maintenance intervals Changing the sealing ring of the outlet flap Servicing the loaderAdjusting the dump valve sensor Cleaning the unit Order numbers Filter cloth Wire cloth Replacing carbon brushes at the motor InstallationMachine-Side Hopper Loaders Disposal Instructions Taking out of service, dismantling, disposalTechnical data Specifications Liter model Brushless motor Loader Capacity Dimension Sheet Liter model Liter brushless model Spare parts list Parts breakdown, brush-type motor 10.2.1 V, 50 Hz Parts lists, 2-liter model10.2.2 V, 60 Hz 10.2.4 V, 60 Hz with active cleaning 10.2.3 V, 50 Hz with active cleaning10.3.1 V, 50 Hz V66372 Parts list, 5-liter modelPos. Order no. Designation 10.3.2 V, 60 Hz V66378US10.3.4 V, 60 Hz with active cleaning 10.3.3 V, 50 Hz with active cleaningParts breakdown and list, 5-liter model with brushless motor 10.5 V, 50 Hz Accessories Page Electrical manual Page Page Page Page Page Page Page Page Page Quick Start Guide Setting the loader convey time