5.1.24Fuel Tank – mounting hardware specification.
When installing the nuts on the fuel tank studs, fully tighten the nyloc nut and back off 1/2 turn. This allows for normal fuel tank expansion and contraction with changes in temperature and fuel levels.
5.1.25Thread locking adhesives such as “Loctite 242” or
a)Pump drive sheave set screws.
b)Square head setscrews on Hydro pump control arms.
c)Sheave retaining bolt in the end of engine crankshaft.
d)Caster wheel spacer nuts
e)Fuel tank bulkhead fitting nuts.
Adhesives such as “Loctite RC/609 or RC/680” or
a)Fuel tank studs, where studs are inserted into tank.
5.1.26Mobil HTS grease (or
a)Between the cutter housing spindle and bearings.
b)Between the cutter housing spindle and sheave.
c)Under top cutter housing bearing guard.
d)Between jackshaft and bearings and jackshaft and sheaves.
5.1.27Dielectric grease is used on all blade type electrical connections to prevent corrosion and loss of contact.
5.2 ADJUSTMENTS
IMPORTANT: Disengage PTO, shut off engine, wait for all moving parts to stop, and remove key before servicing, cleaning, or making any adjustments to the unit.
5.2.1Cutting Height Adjustment.
a)Stop machine and move drive levers out to neutral lock position.
b)Disengage PTO.
c)Raise the deck lever to the transport position (also the 5” (12.7 cm) cutting height position). See Figure 9.
The deck can be raised by pulling the deck lever up and/or by pushing on the deck lift assist lever.
NOTE: When changing cutting height positions, always come to a complete stop and disengage the PTO.
FIGURE 9
CUTTING HEIGHT POSITION
d)Insert height adjustment pin into hole corresponding to desired cutting height and install hairpin cotter. See decal on the side of deck lift plate.
- 32 -