2.4.5Fiber Requirements
Optical fibers are required at the site to provide the physical link between the RAN and the Hub. In a typical installation, the identified fibers are broken out of a
2.5Installing a RAN Cabinet on a Wooden Utility Pole
Figure 25 shows the main components and their spatial placement in a typical NXD RAN pole mount installation.
2.5.1Site Requirements Unique to Pole Mounting Locations
If power lines are present at the top of the pole, spacing requirements applicable to the RF cabling and any other hardware installed in the electric space must be considered. Per the National Electrical Safety Code, vertical clearance at supports for
For supply conductors at voltages up to 8700 between conductors, the minimum horizontal clearance provided by the NESC ANSI C2 is 12 in. (30.5 cm). For higher voltages, it is required that .4 in. (10.2 mm) be added for every 1000V above 8700. Table 18 lists the required clearances for some common high voltages.
| Table 18. Antenna Clearance vs. Voltage | |
|
|
|
VOLTAGE |
| HORIZONTAL CLEARANCE |
8700V |
| 12.0 in. (30.5 cm) |
|
|
|
15 kV |
| 14.52 in. (36.9 cm) |
|
|
|
28 kV |
| 19.72 in. (50.1 cm) |
|
|
|
38 kV |
| 23.72 in. (60.2 cm) |
|
|
|
This information is from the Standard Handbook for Electrical Engineers, 13th Edition, McGraw Hill, Chapter 18, Section 151, Pages