ADCP-75-210 • Issue 1 • March 2007

2.7Other Standard Installation Procedures

This section contains other procedures done at every installation after the RAN is mounted on a wooden pole or concrete pad.

2.7.1Installing a Solar Shield

Each RAN has a solar shield that mounts on top of the cabinet. Hardware for the solar shield can be found in a bag fastened to the inside of the battery compartment. The hardware consists of two 1/4 in. bolts, each with flat washer and sealing washer. Use the following procedure to install the solar shield. Refer to Figure 31.

1.Remove the solar shield from its packaging.

2.Place a lock washer and flat washer and then the sealing washer on each 1/4 in. machine bolt.

3.Using the key provided, open the RAN door.

SOLAR

SHIELD

RUBBER

SEALING

WASHER

TANGS

FLAT

WASHER

1/4 x 20

HEX HEAD

BOLT

EACH SIDE

21339-A

Figure 31. Installing the Solar Shield

Page 43

© 2007, ADC Telecommunications, Inc.