Display Interface
40 Smart Distribution Panel with ATS
Test Sche duleTest Dura tion
Use this menu to schedule a test in the future.
Define Schedule Set the test schedule by changing the following parameters:
Gen Start: Choose when to perform a
generator start test. Choices are Never,
Monthly, Weekly, or Daily.
Day: The choices for Day depend on the
choice made for Gen Start:
If you chose a GenStart of Never: Day is not configurable
If you chose a GenStart of Monthly: Choose to perform the test on the 1st, 2nd,
3rd, or 4th week of the month on a specific day of the week.
If you chose a GenStart of Weekly: Choose to perform the test on any day of the
week.
If you chose a GenStart of Daily: Choose to perform the test Everyday, on
Weekdays (Monday through Friday), or on Weekends (Saturday and Sunday).
Time: Set the time of day that the test will run. The time is set on a 24-hour clock.
Load Test: Choose to test the generator with the data center load applied. Choose
to perform the load test By Month, Monthly, Never, or All.
Next Test Lists the date and time of the next test.
Gen Start: Monthly
Day: 1st Monday
Time: 14:30
Load Test: Monthly
The following items are available on this menu:
Warm Up Set the amount of time in seconds (up to 999) that the generator will warm up
during a test.
Loaded If the option to Load Test is selected, set the amount of time in minutes (up to 999)
that the generator will run with the data center load applied.
Cooldown Set the amount of time in seconds (up to 999) that the generator will cool down
after the test.