Start-Up

Start-Up

Start-up checklist

Before starting the equipment, check to see that the following conditions are met:

All electrical connections comply with national and local codes and safety standards.

All accessories and ductwork have been installed.

Air flow to and from the equipment is not blocked.

The condensate drain is connected and not kinked or pinched.

How to apply power to the equipment

Insert the IEC-320-C19 connector of the power

Circuit breaker

cord into the back of the equipment. Insert the

 

opposite end of the power cord, a NEMA 5-20

 

plug, into the wall outlet. Verify the circuit

 

breaker is pressed in (flush with the rear of the

 

equipment), and the green LED on the back of

 

the plug is on.

 

Electrical Hazard: Do not use extension cords with this equipment. Using an extention cord reduces circuit protection and voids the warranty.

Note: If the equipment has been unplugged or off for less than three minutes, it waits three minutes before starting the compressor.

Warning: Route the power cord and the condensate line to prevent accidental injury to people or damage to the equipment.