START-UP CHECKLIST

(Remove and Store in Job File)

I. PRELIMINARY INFORMATION

MODEL NO.: __________________________________

SERIAL NO.: ______________________________________

DATE: ________________________________________

TECHNICIAN: _____________________________________

BUILDING LOCATION: _________________________

 

II. PRE-START-UP (insert checkmark in box as each item is completed)

VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS

CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS

CHECK THAT RETURN (INDOOR) AIR FILTERS ARE CLEAN AND IN PLACE

VERIFY THAT UNIT INSTALLATION IS LEVEL

CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND SETSCREW TIGHTNESS

CHECK PULLEY ALIGNMENT AND BELT TENSION PER INSTALLATION INSTRUCTIONS

￿VERIFY INSTALLATION OF ECONOMIZER HOOD (IF EQUIPPED)

III.START-UP:

ELECTRICAL

SUPPLY VOLTAGE

L1-L2

 

L2-L3

 

L3-L1

CIRCUIT 1 COMPRESSOR AMPS L1

 

L2

 

L3

CIRCUIT 2 COMPRESSOR AMPS L1

 

L2

 

L3

INDOOR-FAN AMPS

L1

 

L2

 

L3

TEMPERATURES

 

 

 

 

OUTDOOR-AIR TEMPERATURE

 

DB

 

WB

RETURN-AIR TEMPERATURE

 

DB

 

WB

COOLING SUPPLY AIR

 

DB

 

WB

PRESSURES (COOLING MODE)

 

 

 

 

REFRIGERANT SUCTION, CIRCUIT 1

 

PSIG

 

F

REFRIGERANT SUCTION, CIRCUIT 2

 

PSIG

 

F

REFRIGERANT DISCHARGE, CIRCUIT 1

 

PSIG

 

F

REFRIGERANT DISCHARGE, CIRCUIT 2

 

PSIG

 

F

VERIFY THAT 3-PHASE SCROLL COMPRESSOR IS ROTATING IN THE CORRECT DIRECTION (SIZE 012 ONLY) VERIFY REFRIGERANT CHARGE USING COOLING CHARGING CHARTS ON PAGES 48 AND 49.

￿GENERAL

SET ECONOMIZER MINIMUM VENT AND CHANGEOVER SETTINGS TO MATCH JOB REQUIREMENTS (IF EQUIPPED)

Copyright 2005 Carrier Corporation

Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.

Book

1

4

Catalog No. 04-53500019-01

Printed in U.S.A.

Form 50TFQ-9SI

Pg CL-1

9-05

Replaces: 50TFQ-7SI

Tab

5a

5a

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - CUT ALONG DOTTED LINECUT ALONG DOTTED LINE

Page 56
Image 56
Carrier 50TFQ008-012 specifications START-UP Checklist, Preliminary Information, Iii. Start-Up