CM2 | Installation Instructions |
Cable Installation and Routing
The CM2 has an integrated cable management system that allows cables to be automatically "fed out" as the lift raises, and "reeled in" as the lift lowers while maintaining constant cable tension.
IMPORTANT ! : The CM2 requires minimum cable lengths of 8 feet from display through lower mount.
To install cables:
1.Remove two screws securing cable guide side cover.
2.Set screws aside for reuse. (See figure 17)
1 |
x2 |
Cable Guide |
Side Cover |
Figure 17
3.Slide cable guide side cover away from mount and carefully set aside.
Cable Guide |
Side Cover |
3 |
Figure 18
4.Loosen six cable clamps. (See figure 19)
5.Route cable(s) down through upper cable clamp. (See figure 19) and (See figure 20)
IMPORTANT ! : Leave enough cable length available above upper cable clamp to allow the routing and