Chapter 3 Bringing Up the Cisco IOS XR Software on a Multishelf System

Bringing Up and Verifying FCCs

DETAILED STEPS

 

Command or Action

Purpose

Step 1

 

 

Apply power to all FCCs.

Starts the FCCs.

 

 

Allow each FCC to fully boot.

 

 

Verify that “IOS XR RUN” appears on the

 

 

SC faceplates.

 

 

Verify that the indicator LED on the OIM

 

 

LED panel is green for each fabric cable

 

 

connected to Rack 0.

 

 

Each FCC loads any required software

 

 

and configurations from the DSC,

 

 

including the rack number and

 

 

appropriate Cisco IOS XR software

 

 

packages.

 

 

Do not proceed until both SCGEs in each

 

 

FCC display “IOS XR RUN.” This

 

 

message indicates that each SCGE has

 

 

successfully loaded the Cisco IOS XR

 

 

software.

Step 2

 

 

show controllers fabric rack all detail

Displays the status of all racks in the system.

 

 

In a properly operating system, the rack

 

Example:

status for all racks should be Normal, and

 

RP/0/RP0/CPU0:router(admin)# show controllers fabric rack

the server status should be Present.

 

all detail

 

Step 3

 

 

show controllers fabric plane all detail

Displays the status of all racks and additional

 

 

information for racks in installation mode.

 

Example:

Wait for the status in the Admin State and

 

RP/0/RP0/CPU0:router(admin)# show controllers fabric plane

Oper State columns to change to UP for

 

all detail

all planes.

 

 

 

 

 

Cisco IOS XR Getting Started Guide

 

 

 

 

 

 

OL-10957-02

 

 

3-35

 

 

 

 

 

Page 73