Installation Guide for the PVS 200, 300, and
PoleVault Systems
68-1390-01
Rev. D
Precautions
Safety Instructions English
Consignes de Sécurité Français
Sicherheitsanleitungen Deutsch
PoleVault Systems Installation Introduction
Introduction
Overview
The PoleVault System
PoleVault System installation and wiring overview
1-2 PoleVault Systems Installation Introduction
Introduction, contd
Extron Cables & Notes
Before you Begin Installation - Planning
Typical classroom installation
PoleVault Systems Installation Introduction - Planning
1. Room layout
Example of a classroom installation
1-4 PoleVault Systems Installation Introduction - Planning
Introduction - Planning, cont’d
b. Location of the screen and projector
Example classroom with four speaker installation
Viewing obstructions
c. Location of MediaLink Controller and Wall Plates
Location of source devices
1-6 PoleVault Systems Installation Introduction - Inventory Overview
Introduction - Inventory Overview
2. Inventory
a. Included items
PoleVault Systems Installation Introduction - Inventory Overview
PoleVault System Devices and Hardware, contd
PoleVault System Devices and Hardware, cont’d
PVT CV D
1-8 PoleVault Systems Installation Introduction - Inventory Overview
Introduction - Inventory Overview, cont’d
PoleVault System Ceiling Speakers
PV SI 3C LP
b. Items not included
PoleVault Systems Installation Introduction - Inventory Overview
Document camera and cables
d. Installation tools
Introduction - Inventory Overview, cont’d
Installation Overview
Outline of installation steps
Stage One - Install the Screen and Projector
Stage Three - Install the PV SI 3C LP Ceiling Speakers
Where it goes Screws up into PCM
Adjuster Plate
2-2 PoleVault Systems Installation Installation - Stage
PCM 240 Projector Ceiling Mount
When marking the center line of the screen
PMP installed onto PCM
2c Install the PMP
2d Screw the adjuster plate onto the PMP
Installation - Stage One, cont’d
2f Slide and lock the projector onto the adjuster plate
2-4 PoleVault Systems Installation Installation - Stage
3. Verify the image location
installation
4. Cut the ceiling tile
4b Take measurements with the PCM 240 on the T-bar
Mark and start cutting the hole on the
6b Mark structural ceiling for lag bolt installation
2-6 PoleVault Systems Installation Installation - Stage
6. Secure the Projector Ceiling Mount to the ceiling
6a Attach turnbuckles at the corners
7. Install the Screen
6g Attach the safety cable to the PCM
T Power outlet installation on the PCM
T Use S-hooks to hang the screen from the brackets
Stage Two - Install the Wall Plates and MLC 104 IP
This stage involves installing the devices shown below
2-8 PoleVault Systems Installation Installation - Stage
Stage
PVT transmitter installation
MLC 104 IP Plus installation
PVS 204SA switcher
Cables
Stage Two - Install the Wallplates and MLC 104 IP Plus
1. Install mud rings
If a suitable wall box is already installed, follow step 2 onwards
T Use a level when marking the holes
Signal Cable
2. Pull cables
T Secure cables with cable clamps to provide strain relief
Label color
Installation - Stage Two, cont’d
3. Install wall plates
2-12 PoleVault Systems Installation Installation - Stage
3b Mount the PVT in the mud ring, then
4. Install MediaLink Controller
TWire stripping lengths
Wire color
4a Connecting the MLC to the switcher
4c Connect to the LAN using a CAT 5 cable
2-14 PoleVault Systems Installation Installation - Stage
Connect the MLC to the projector with
an RS-232 cable or IR emitter cable, as
Connections made to the MLC 104 IP Plus
4e Secure the MLC 104 IP Plus to the mud ring
2-15
PoleVault Systems Installation Installation - Stage
Stage Three - Install the PV SI 3C LP Ceiling Speakers
Speaker Installation
Speaker cable connects ceiling speakers to the PVS 204SA switcher
2-16 PoleVault Systems Installation Installation - Stage
1. Cut ceiling tile
Measure and mark the center point of the tile and align
1b Mark the tile and cut the hole
the cross marks with those on the supplied template
Installation - Stage Three, cont’d
2-18 PoleVault Systems Installation Installation - Stage
4. Cable the speakers
2e Turn and lock down the four dog legs on the C‑ring
4-pole captive screw connector
4c Wire the captive screw connector Dual mono output
Stereo or dual mono output using parallel speaker wiring
c. To terminate the cable, strip the end of the cable
5. Finish speaker installation
2-20 PoleVault Systems Installation Installation - Stage
5a Apply putty to speaker grill
Installation - Stage Three, cont’d
Stage Four - Install the PMK 450 and the PVS 204SA
This stage covers installing the devices shown below
PVS 204SA PoleVault Switcher
PoleVault Systems Installation Installation - Stage 4
Installation - Stage Four, cont’d
2. Install the PMK 450 Pole Mount kit
Switcher and projector cable overview
2-22 PoleVault Systems Installation Installation - Stage
3. Install the PVS 204SA switcher
to the cord of the supplied power source and connect the
power cord to the rear of switcher
3c Wire the captive screw connector for the power supply
4. Finish installing the Pole Mount kit
BControl/power cable from the MLC 104 IP Plus
FPower supply cable. Do not apply power yet
N Do not thread the power cable through the
4d Replace projector on the adjuster plate
4c Attach and screw down rear plate
PoleVault Systems Installation Installation - Stage 4
Stage Five - Configure the System
1. Configure the system
1a Load Global Configurator 2 software
1c Launch the Global Configurator 2 program
Select MLC 104 IP Plus/PoleVault System from the drop down box
2-27
PoleVault Systems Installation Installation - Stage
Installation - Stage Five, cont’d
2a Turn on the MLC 104 IP Plus controller and the PVS 204Sa switcher
2c Check that an image is present, adjust as needed
2-28 PoleVault Systems Installation Installation - Stage
3. Final installation
2e Set MLC volume to maximum, and adjust the level on the switcher
2-29
PoleVault Systems Installation Installation - Stage
Optional Accessory Installation - PPC
Installation Procedure
4 Open the sensor and loop a wire around the sensor
2-30 PoleVault Systems Installation Optional Accessory Installation
PoleVault Systems Installation Optional Accessory Installation
7. Strip 3/16 of insulation from each conductor on the bare
10 Connect the power supply via the PoleVault switcher
2-32 PoleVault Systems Installation Optional Accessory Installation
Optional Accessory Installation - PPC
Testing and Adjustment Procedure
3 / 4 Sensitivity knob adjustment
5 Priority Page Controller Time DIP switch settings
PoleVault Systems Installation Optional Accessory Installation
Specifications
N Specifications are subject to change without notice
2-34 PoleVault Systems Installation Reference Information
Reference Information
PoleVault Systems Installation Reference Information
Devices PVS 204SA
MLC 104 IP Plus
PVT CV D and PVT RGB D
Installation - Reference Information, cont’d
PoleVault Switcher
16-18 lbs 7.3-8.2 kg Projector weight must not exceed 25 lbs 11.3 kg
2-36 PoleVault Systems Installation Reference Information
Page
Outline of installation steps
Stage One - Install the Screen and Projector
Stage Three - Install the PV SI 3C LP Ceiling Speakers
Stage Four - Install the PMK 450 and the PVS 204SA