1.8 Installing the Attachment Kit (option)

The attachment kit permits use of the tank for the CSH-20 series using the 1600 mm stroke transducer and FSV-243E/244E.

Attachment kit (Type: OP10-24, Code no.: 006-943-530)

Name

Type

Code No.

Qty

Insulation gasket (1)

MS-1000-67

000-857-220

24

Insulation gasket (2)

MS-1000-68

000-857-221

24

1.Clean the hull unit flange, the O-ring and O-ring groove. Coat them with a slight amount of grease. Place the O-ring in position on the tank flange.

2.Lay the insulation gasket (1) on the top of the tank flange.

3.Orient the hull unit so that the bow mark (inscribed) on its flange points toward the ship’s bow. Note that heading adjustment in the monitor is required if the bow mark does not face the ship’s bow.

4.Confirm that the O-ring and the insulation gasket (1) are in position.

5.Place the hull unit on the tank.

6.Seven of the 24 bolt holes on the hull unit flange have already been fitted with bolts (stern side). Insert the insulation gasket (2) into the bolt holes of the tank flange to which these seven bolts are fitted.

7.Coat every bolt, washer and nut with a slight amount of grease to ease removal. Fit the insulation gasket (2) into the bolt holes of the tank flange. Fasten the hull unit to the retraction tank with insulation gasket (2), flat washers, spring washers and hex bolts.

8.Reinforce the hull unit against vibration by extending stays to the ship’s hull from the two eye bolts at the top of the hull unit, referring to the figure at the top of page 1-8.