Guardian Technologies 5308, 4582 & 4987, 4583 Test 11 Excitation Wiring, Test 12 Check Brush Leads

Models: 5308 4583 4451 & 4986 4582 & 4987

1 90
Download 90 pages 17.81 Kb
Page 47
Image 47

Section 6

DIAGNOSTIC TESTS

TEST 11 - EXCITATION WIRING

PROCEDURE:

1.Set a voltmeter to measure resistance.

2.Disconnect Connector C1. See Page 17 for connector location.

3.Locate the male side of the connector located on the bottom of the control panel. See Figure 6-19. Connect one meter test lead to Pin 6 Wire 2, it may be helpful to connect a small jumper lead to the individual pin. Disconnect Wire 2 from the Excitation Circuit Breaker (CB1). Connect the other meter test lead to Wire 2 . See Page 17 for Excitation Circuit Breaker loca- tion. Continuity should be measured.

4.Unplug the six pin connector at the Voltage Regulator.

5.Locate the male side of the C1 connector located on the bot- tom of the control panel. Connect one meter test lead to Pin 7, Wire 6. It may be helpful to connect a small jumper lead to the individual pin. Connect the other meter Test lead to Wire 6 located in the six pin connector previously removed from the Voltage Regulator. Be careful not to damage the pin connectors with the test leads. Continuity should be measured.

RESULTS:

1.If continuity was not measured in any of the steps repair or replace wire.

2.If all steps pass refer back to flow chart.

TEST 12 - CHECK BRUSH LEADS

PROCEDURE:

1.Set a voltmeter to measure resistance.

2.Disconnect Connector C1. See Page 17 for connector location.

3.See Figure 6-18. Connect the meter test leads across Wire 4 (Pin 11) and Wire 0 (Pin 12) at the C1 connector female side. Be careful not to damage the pin connectors with the test leads, use paper clips - do not force probes into connectors. Rotor resistance should be measured approximately 7-14 ohms. If resistance is measured proceed to Step 6. If no resis- tance is measured continue.

4.Remove the control panel assembly to access the brushes. See Figure 6-21. Connect one meter test lead across Wire 4 (Pin 11) at the C1 connector female side. Be careful not to damage the pin connectors with the test leads, use paper clips - do not force probes into connectors. Connect the other meter test lead to Wire 4 at the brush assembly. Continuity should be measured. If INFINITY is measured repair or replace Wire 4.

5.Connect one meter test lead across Wire 0 (Pin 12) at the C1 connector female side. Be careful not to damage the pin connectors with the test leads, use paper clips - do not force probes into connectors. Connect the other meter test lead to Wire 0 at the brush assembly. Continuity should be measured. If INFINITY is measured repair or replace Wire 0.

6.Unplug the six pin connector at the Voltage Regulator.

7.Locate the male side of Connector C1 located on the bottom of the control panel. See Figure 6-19. Connect one meter test lead to Pin 11 Wire 4. Connect the other meter test lead to Wire 4 at the six pin connector previously removed from the Voltage Regulator. See Figure 6-11. Be careful not to damage the pin connectors with the test leads. Continuity should be measured. If continuity is not measured repair or replace Wire 4 between the C1 connector and the six-pin Voltage Regulator connector.

8.Connect one meter test lead to Pin 12 Wire 0. See Figure 6-19. Connect the other meter test lead to the ground terminal in the control panel. Continuity should be measured. If continuity is not measured repair or replace Wire 0 between the C1 connec- tor and the ground terminal.

RESULTS:

1.Repair or replace wiring/terminals as needed.

2.If no faults are found refer to flow chart.

4 0

Figure 6-20. – Brush Leads

Test 13 - Check Brushes & Slip Rings

PROCEDURE:

1. Gain access to the brushes and slip rings.

Page 45

Page 47
Image 47
Guardian Technologies 5308, 4583 Test 11 Excitation Wiring, Test 12 Check Brush Leads, Test 13 Check Brushes & Slip Rings