Section 6
DIAGNOSTIC TESTS
00.00
SW2
83
0
|
|
|
|
|
|
|
|
|
|
MAKE SURE THE TEST PROBE CONNECTOR IS
MAKING CONTACT WITH THE CONNECTOR.
DOUBLE CHECK TO
J2 HARNESS CONNECTOR MAKE SURE THAT THE TIP IS SHARP.
Figure 6-60. – Check Idle Control Wiring
RESULTS:
Repair or replace wiring as needed. Refer back to the flow chart.
Test 54 - Check Idle Control
Transformers (ICT)
PROCEDURE:
7.Apply a light load to the generator, such as a electric drill.
8.When the drill is activated measure the voltage output. The AC voltage should measure around
RESULTS:
Refer back to flow chart.
|
| BLK | BLK |
86 | 15B | 167 |
|
0 | 229 | 83 | 100 ohm |
TERMINAL | TR2 |
| |
BLOCK |
| TR1 |
|
(TB1) |
|
|
|
Figure 6-61. Check Idle Transformer Wiring
TEST 55 - CHECK TR1 & TR2 Wiring
86 15B 167 BLK
0 | 229 | 83 | BLK |
00.00
TB1 | TR2 |
| TR1 |
1. | Set a voltmeter to measure resistance. |
2. | Remove the two Idle Control Transformer (ICT) Wires from |
| Terminal Block 1 (TB1). See Figure |
3. | Connect one meter test lead to one wire and connect the other |
| meter test lead to the other wire. Approximately 100 ohms |
| should be measured. If resistance is not measured repair or |
| replace the Idle Control Transformers. If resistance was mea- |
| sured proceed with Step 4. |
4. | Set a voltmeter to measure AC Voltage. |
5. | Connect one meter test lead to one wire and connect the other |
| meter test lead to the other wire. |
J2 HARNESS CONNECTOR
MAKE SURE THE TEST PROBE CONNECTOR IS MAKING CONTACT WITH THE CONNECTOR. DOUBLE CHECK TO MAKE SURE THAT THE TIP IS SHARP.
6. Turn the Idle Control Switch (SW2) to OFF. The generator |
should be running at about 60 HZ. |
Figure 6-62. – Check TR2 Wiring
Page 64