17

This shows an attic installation.

1.Keep insulation away from the vent pipe at least 1 inch (25 mm).

If the area above the ceiling IS an attic, position and secure the firestop on top of the previously framed hole.

NAILS (4 REQUIRED)

RAFTER

CEILING

CEILING FIRESTOP

Figure 17. Attic Firestop

C. Vent Termination

For Horizontal Terminations - To attach and secure the termination to the last section of horizontal vent:

Rotate and interlock the ends as described at the beginning of the Installing Vent Components sec- tion.

The termination kit should pass through the wall firestops from the exterior of the building.

Adjust the termination cap to its final exterior posi- tion on the building.

WARNING

THE TERMINATION CAP MUST BE POSITIONED SO THAT THE ARROW IS POINTING UP.

For roundcap termination kits:

Use the exterior pipelock hole provided on the round flange of the wall firestop to secure the vent pipe in place.

For trapezoidal cap termination kits:

Using screws, secure the cap to the exterior wall through the flanges built into the cap.

Use a high-temperature sealant or fiberglass rope gasket to seal between the 8-5/8 inch

(219 mm) pipe and exterior firestop.

Page 20
Image 20
Heat & Glo LifeStyle 6000 GDVFL, 6000 XLS manual Vent Termination, Attic Firestop