HP Performance Optimized Data Center (POD) 240a manual Description Yes Initial

Models: Performance Optimized Data Center (POD) 240a

1 39
Download 39 pages 18.56 Kb
Page 26
Image 26

Item

Description

Yes

No

N/A

 

Initial

 

 

 

 

 

 

 

 

 

11. Support

Physically evaluate the delivery path that is required with the

 

 

 

 

 

 

infrastructure for

customer's site engineering personnel to identify any

 

 

 

 

 

 

access requirements

obstacles that might be encountered during the site visit.

 

 

 

 

 

 

12. Site engineering

Review and document the following items with the site

 

 

 

 

 

 

review

engineering personnel:

 

 

 

 

 

 

 

Delivery

 

 

 

 

 

 

 

Staging

 

 

 

 

 

 

 

Installation

 

 

 

 

 

 

 

Utilities

 

 

 

 

 

 

 

Commissioning requirements

 

 

 

 

 

 

 

 

 

 

 

 

 

 

13. Capacity of

Review the electrical requirements of the HP POD 240e NA

 

 

 

 

 

 

electrical

with the customer and the customer's site engineering

 

 

 

 

 

 

infrastructure

personnel.

 

 

 

 

 

 

 

HP is not responsible for customer site infrastructure unless it

 

 

 

 

 

 

 

is stated in the SOW.

 

 

 

 

 

 

14. Adiabatic

Determine pressure, temperature, instantaneous flow rate,

 

 

 

 

 

 

media water

type, and source of the proposed media water. Be sure the

 

 

 

 

 

 

 

site parameters are within or will be within specifications

 

 

 

 

 

 

 

before installation.

 

 

 

 

 

 

15. Access control

Review site access and security procedures with the

 

 

 

 

 

 

 

customer's site engineering personnel. Be sure sufficient

 

 

 

 

 

 

 

access is available to HP's installation team.

 

 

 

 

 

 

16.

Following the HP installation site visit, analyze the data that is

 

 

 

 

 

 

Recommendations

collected and prepare a report of findings. HP must identify

 

 

 

 

 

 

 

potential obstacles to installation and make

 

 

 

 

 

 

 

recommendations for any additional testing or changes to

 

 

 

 

 

 

 

the installation plan.

 

 

 

 

 

 

Customer responsibilities

 

 

 

 

 

 

 

 

 

 

 

 

Item

Description

 

 

 

Initial

 

 

 

 

 

 

1. Point of contact

Provide HP with the name and telephone number of the designated point of

 

 

 

information

contact for the purposes of this service.

 

 

 

 

 

 

2. Service listing

Provide all information that is required under this service listing or reasonably

 

 

 

information

determined by HP to be necessary to deliver the service, including but without

 

 

 

 

limitation, any documentation (internal or external) regarding prior plans or

 

 

 

 

investigations used to identify the proposed installation site.

 

 

 

 

 

 

3. Timely response

Provide a timely response (such as, in a time period that does not adversely

 

 

 

 

affect the HP scheduled performance of the service) to all requests for

 

 

 

 

information by HP.

 

 

 

 

 

 

4. Access to subject

Provide HP access to all subject areas and support areas, including the

 

 

 

areas and support

proposed installation site and the mechanical or electrical infrastructure

 

 

 

areas

provided to support the HP POD 240e NA.

 

 

 

 

 

 

5. Badge access

Provide HP badge access or an escort for the duration of the site visit to

 

 

 

 

facilitate required access to all necessary areas.

 

 

 

 

 

 

6. Site engineering

Be sure that your site engineering personnel are familiar with the proposed

 

 

 

personnel

installation site. The personnel that are responsible for the maintenance and

 

 

 

 

support of the existing infrastructure must be available to answer questions.

 

 

 

7. Documentation

Provide HP with copies of all available mechanical and electrical system

 

 

 

 

design documentation, including as-built drawings and electrical single-line

 

 

 

 

drawings. As appropriate to the specific location, provide HP with campus

 

 

 

 

maps, building drawings, floor plans, and other relevant prints to assist in the

 

 

 

 

documentation and evaluation of the proposed installation site.

 

 

 

 

 

Appendix A: HP site assessment 26

Page 26
Image 26
HP Performance Optimized Data Center (POD) 240a manual Description Yes Initial