Item  | Description | 
 | 
  | 
  | 
  | 
7  | Verify the average local temperatures and be sure that  | 
  | 
  | adequate environment protection is provided. For example,  | 
  | 
  | verify that cold weather protection is provided, if necessary.  | 
  | 
8  | Verify that site altitude is less than 3.048 meters (10,000 feet).  | 
  | 
9  | When installing on an elevated surface:  | 
  | 
  | • Verify that the maximum height requirements for the circuit  | 
  | 
  | breaker actuator meet the local and national electric code  | 
  | 
  | requirements of 200 cm (79 inch) (NEC   | 
  | 
  | • Verify that proper landings and catwalk are planned for  | 
  | 
  | electrical cabinet access.  | 
  | 
  | 
  | 
  | 
10  | Verify that the planning for the required egress includes routes  | 
  | 
  | for all HP POD 240e NA personnel doors, cargo doors, and  | 
  | 
  | service area doors, including landings, catwalk, and stairs.  | 
  | 
11  | Verify that the local AHJ has been contacted, all applicable  | 
  | 
  | codes and   | 
  | 
  | reviewed, and all required permits are obtained.  | 
  | 
12  | Verify that the site location has clearances ("Dimensions and  | 
  | 
  | required clearances" on page 7) for HP POD 240e NA  | 
  | 
  | installation, including any permanent structures, such as fences,  | 
  | 
  | walls, vestibules, and buildings.  | 
  | 
13  | Verify that all utilities, overhead and underground, are  | 
  | 
  | identified to maintain required clearance.  | 
  | 
14  | Verify that there is adequate clearance around the HP POD  | 
  | 
  | 240e NA for door operation, installation, and maintenance  | 
  | 
  | equipment.  | 
  | 
15  | Verify that the site location and site pads are marked for  | 
  | 
  | 
  | |
16  | Verify that a truck and equipment staging area has been  | 
  | 
  | identified. Verify planning for trucks for the HP POD 240e NA  | 
  | 
  | and other equipment.  | 
  | 
17  | Verify that locations are available and identified for all  | 
  | 
  | equipment that is required.  | 
  | 
18  | Verify the locations for crane   | 
  | 
  | HP POD 240e NA installation.  | 
  | 
19  | Verify that the location for the storage area and the disposal of  | 
  | 
  | packaging materials and trash are identified.  | 
  | 
20  | Verify that safety equipment is planned for and in place.  | 
  | 
21  | Verify the customer's interfaces of the HP POD 240e NA fire  | 
  | 
  | alarm, security system, and communications systems to site  | 
  | 
  | system. The customer is responsible for all connections.  | 
  | 
22  | Verify that existing contaminated or hazardous materials and  | 
  | 
  | work related to them are disposed of properly.  | 
  | 
23  | Verify that there is an available temporary or permanent load  | 
  | 
  | bank, if required.  | 
  | 
24  | Verify that   | 
  | 
  | POD 240e NA and power containers are completed at least  | 
  | 
  | one week prior to the arrival of   | 
  | 
Water supply
Appendix B: Preparing for delivery 29