Item | Description |
|
|
|
|
7 | Verify the average local temperatures and be sure that |
|
| adequate environment protection is provided. For example, |
|
| verify that cold weather protection is provided, if necessary. |
|
8 | Verify that site altitude is less than 3.048 meters (10,000 feet). |
|
9 | When installing on an elevated surface: |
|
| • Verify that the maximum height requirements for the circuit |
|
| breaker actuator meet the local and national electric code |
|
| requirements of 200 cm (79 inch) (NEC |
|
| • Verify that proper landings and catwalk are planned for |
|
| electrical cabinet access. |
|
|
|
|
10 | Verify that the planning for the required egress includes routes |
|
| for all HP POD 240e NA personnel doors, cargo doors, and |
|
| service area doors, including landings, catwalk, and stairs. |
|
11 | Verify that the local AHJ has been contacted, all applicable |
|
| codes and |
|
| reviewed, and all required permits are obtained. |
|
12 | Verify that the site location has clearances ("Dimensions and |
|
| required clearances" on page 7) for HP POD 240e NA |
|
| installation, including any permanent structures, such as fences, |
|
| walls, vestibules, and buildings. |
|
13 | Verify that all utilities, overhead and underground, are |
|
| identified to maintain required clearance. |
|
14 | Verify that there is adequate clearance around the HP POD |
|
| 240e NA for door operation, installation, and maintenance |
|
| equipment. |
|
15 | Verify that the site location and site pads are marked for |
|
|
| |
16 | Verify that a truck and equipment staging area has been |
|
| identified. Verify planning for trucks for the HP POD 240e NA |
|
| and other equipment. |
|
17 | Verify that locations are available and identified for all |
|
| equipment that is required. |
|
18 | Verify the locations for crane |
|
| HP POD 240e NA installation. |
|
19 | Verify that the location for the storage area and the disposal of |
|
| packaging materials and trash are identified. |
|
20 | Verify that safety equipment is planned for and in place. |
|
21 | Verify the customer's interfaces of the HP POD 240e NA fire |
|
| alarm, security system, and communications systems to site |
|
| system. The customer is responsible for all connections. |
|
22 | Verify that existing contaminated or hazardous materials and |
|
| work related to them are disposed of properly. |
|
23 | Verify that there is an available temporary or permanent load |
|
| bank, if required. |
|
24 | Verify that |
|
| POD 240e NA and power containers are completed at least |
|
| one week prior to the arrival of |
|
Water supply
Appendix B: Preparing for delivery 29