Item  | Description | |||
  | 
  | 
  | 
  | |
1  | Verify that the HP POD 240e NA is not in a drainage path or  | 
  | ||
  | flood prone area to prevent water from entering the HP POD  | 
  | ||
  | 240e NA. HP recommends setting the HP POD 240e NA on a  | 
  | ||
  | raised site pad.  | 
  | ||
2  | Verify that the water quality meets drinking water standards.  | 
  | ||
Adiabatic media water supply | 
  | |||
  | 
  | 
  | 
  | |
Item  | 
  | Description | 
 | |
  | 
  | 
  | 
  | |
1  | 
  | Verify that the water pressure is between   | 
  | |
  | 
  | kPa) and that water temperature is between 1°C to 30°C  | 
  | |
  | 
  | (34°F to 86°F).  | 
  | |
2  | 
  | Verify that the water instant   | 
  | |
  | 
  | 
  | flow of the fill solenoid valve (1.5 gpm maximum flow per  | 
  | 
  | 
  | 
  | adiabatic unit, maximum instantaneous.)  | 
  | 
3  | 
  | Verify that water hardness is no greater than 40degFH or  | 
  | |
  | 
  | equal to 400 ppm of CaCO3.  | 
  | |
4  | 
  | Verify that demineralized water (preferred) or drinking  | 
  | |
  | 
  | (potable) water is used.  | 
  | |
Power requirements | 
  | |||
  | 
  | 
  | ||
Item  | Description | 
 | ||
  | 
  | 
  | ||
1  | Verify that the following requirements are complete:  | 
  | ||
  | •  | Short circuit analysis  | 
  | |
  | •  | Arc flash study  | 
  | |
  | • Circuit breaker coordination studies  | 
  | ||
  | 
  | 
  | ||
2  | Verify that the power installation work is completed according  | 
  | ||
  | to the approved conduit routing drawings that show the exact  | 
  | ||
  | routes, plan view, sections, and elevations.  | 
  | ||
3  | Verify that temporary site power for installation and  | 
  | ||
  | construction is planned and available.  | 
  | ||
4  | Verify adequate site power (on page 13) per HP POD 240e  | 
  | ||
  | NA requirements.  | 
  | ||
General | 
  | 
  | ||
  | 
  | 
  | ||
Item  | Description | 
 | ||
  | 
  | 
  | ||
1  | Verify the utility connection including the main utility  | 
  | ||
  | transformers and metering equipment.  | 
  | ||
2  | Verify the   | 
  | ||
  | required by the owner.  | 
  | ||
3  | Verify that the HP Project Team activities are coordinated with  | 
  | ||
  | other site construction activities.  | 
  | ||