Appendix B: Preparing for delivery

Pre-delivery tasks

Allow adequate time for planning, scheduling, obtaining permits, design approval, inspections, and so on.

Installation prerequisites

Before installing the HP POD 240e NA, verify that the following prerequisites are met:

All components are delivered to the facility.

The HP POD 240e NA and power distribution components are in the final location.

Facility power, water, and drainage are at the final location.

Provisions for properly grounding the HP POD 240e NA are made.

Required clearances exist, including overhead.

All trade personnel required for assembly are coordinated.

HP POD 240e NA site readiness checklist

Before installing the HP POD 240e NA, follow all steps listed in this guide, the site plan, and the following checklists.

Architectural/environmental considerations

Item

Description

Sign-off

 

 

 

 

 

1

Be sure that the following installation requirements are met and

 

 

 

understood by the customer:

 

 

 

POD load pads are in the proper location.

 

 

 

Upon installation, the POD structure must be leveled to ≤

 

 

 

0.5º, which can be checked at that time with a surveyor’s

 

 

 

transit.

 

 

 

Shimming is only allowed at the load pads.

 

 

 

Place shims in increments across the load pads to be sure

 

 

 

that there is sufficient load transfer.

 

 

 

 

 

 

2

Verify that the installation pad is capable of supporting the total

 

 

 

POD solutions weight.

 

 

3

Verify that the HP POD 240e NA site has provisions for

 

 

 

grounding or a grounding system.

 

 

4

Verify that the site pad is physically marked with the locations

 

 

 

of all HP POD 240e NA load pads.

 

 

5

Verify that the HP POD 240e NA is not in the direct path of any

 

 

 

external heat loads, such as generators or a building AHU.

 

 

6

Verify that the installation starting point has been identified and

 

 

 

marked. This is the location where the first HP POD 240e NA

 

 

 

section is placed during installation.

 

 

 

 

Appendix B: Preparing for delivery 28