Equipment Location 9
5.0 EQUIPMENT LOCATION
1. Handle cabinet(s) in accordance with the Section 1.0 Safety Precautions and 3.0
Unloading & Hand ling. Use a suitable material handling device to move cabinet to its final
location. Exercise extreme care because of the uneven weight distribution.Carefully
lower the cabinet to the floor.
2. Verify that the UPS system is installed in a clean, cool and dr y location.
3. Installation and serviceability will be easier if adequate access is provided on all sides of the
equipment, but only frontaccess is required.
a. Verify that there is adequate clearance to open cabinet doors. See drawings and local
codes (4 feet is recommende d).
b. Verifythat there is adequate area in front of circuitbreakers to perform maintenance.
Check installation drawingsfor location of breakers. Check with local codes.
c. Verify that there is ade quate clearance above all cabinets to allow exhaust air to flow
without restriction(2 feet minimum, unobstructed).