3.6.12 Intake Duct Terminations

MACH® Series Gas-Fired BoilerInstallation

Exhaust Vent

3.6.12 Intake Duct Terminations

(Sidewall

 

Venting

Roof

Requires Up

 

Elbow Mounted)

 

 

Round

Air inlet

 

(Down Elbow

 

Mounted)

90° Elbow

Sidewall

 

C750/900/1050 Sidewall Inlet and Vent

 

3.6.9 Intake Duct Materials and Sizes:

Material: PVC, CPVC (Schedule 40), single wall galvanized steel, or other suitable materials.

The intake duct must be sized for a maximum pressure drop of 0.22 inches W.C., for the SCFM as specified below.

Boiler Size

Required SCFM

 

 

1050

245

 

 

900

210

 

 

750

175

 

 

450

105

 

 

300

70

 

 

The installation of a bird screen on the intake termination is recommended.

3.6.10 Sealing the Intake Duct

Proper sealing of the intake ductwork is necessary to prevent infiltration of air from conditioned space. Joints in PVC or CPVC must be cemented. For galvanized duct, wrap each joint and seam with adhesive aluminum tape.

Sidewall

Air Inlet

(tee mounted horizontally)

Round

No rain cap -

Unrestricted

3.6.11 Intake Duct Connection to Boiler

Connect the air supply duct to the collar on the back of the boiler. Fasten the duct to the collar with sheet metal screws at 90º angles. Seal the joint.

The roof intake termination must be an unrestrictive type, as shown above.

Page 12

Page 16
Image 16