Blast Chiller Installation Checklist

Model RBC50

1)Insure proper clearances, no obstruction to either front louver for at least 24from cabinet face.

2)Install all eight legs or casters, insuring that the unit is level for proper operation (see section III d. for more details).

3)Install the control panel (see section III n. for more details). Before doing so be sure to perform a visual inspection of the control to insure that no connections have come loose during shipment.

4)Plug both power cords into separate, dedicated 115 volt/20 amp outlets (see section III f. for more details).

5)Insure that paper supply for both printers are properly installed and that the printers themselves are operational (see section IV c. for more details).

Model RBC100

1)Insure proper clearances, no obstruction to either front louver for at least 24from cabinet face, 6along left side, 4along the right side, and 6behind the unit

2)Install the legs or casters, insuring that the unit is level for proper operation (see section III d. for more details).

3)Make condensate removal provisions (see section III h. for more details).

4)Hardwire the cord to a dedicated 220/60/1 volt, 4 wire, 20 amp circuit (see section III g. for more details).

5)Insure that paper supply for both printers are properly installed and that the printers themselves are operational (see section IV c. for more details).

Models RBC200 & RBC200RT (same for models RBC400 & RBC400RT but please see section III e. for additional installation/assembly instructions)

1)Insure proper clearances, no obstruction to either front louver for at least 12above the cabinet and 4along the right side (for the drain tube). Unit must be located on a level surface.

2)Seal the unit to the floor (see section III l for more details).

3)Install the door ramp(s), (see section III l. for more details).

4)Make condensate removal provisions (see section III h. for more details). Note that two drain outlets are provided. Please insure that the unused drain line is properly plugged to prevent leaks.

5)Plug the power cord into a dedicated 115 volt/20 amp outlets (see section III g. for more details).

IMPORTANT NOTE

In order to accomplish blast chilling, models RBC200 and RBC200RT require one, and models RBC400 and RBC400RT require two properly sized remote condensing units (see section III j. for more details). After this installation has been completed by a qualified refrigeration technician, please call Traulsen Service at (800) 825-8220 in order to arrange for your free on-site installation validation.

6)In order to properly charge the system, at the completion of installation this must be run in blast chill mode for at least 90-minutes. To do so...

`1- Select: BY TIME from the main menu.

2- Then select the default setting CHILL (default) or scroll up or down to select this mode.

3- Next select the default cycle time 01:30 (1 hour & 30 minutes) or scroll up or down to select this time.

4- Finish by selecting START to initiate the test cycle.

7)Insure that paper supply for both printers are properly installed and that the printers themselves are operational (see section IV d. for more details).

GENERAL NOTE:

In the event that the owners manual is not available, please visit www. traulsen.com in order to view/print the latest version.

MAIN MENU

AIR 35°F

 

BY TEMP

BY PROD

 

 

 

 

 

BY TIME

 

08:05:01

 

MORE

BY TIME

 

 

 

 

 

TYPE: CHILL

 

CYCLE TIME:

01:30

 

MAIN

START

BY TIME

TYPE: CHILL

CYCLE TIME: 01:30

MAIN

START

BY TIME

 

 

TYPE: CHILL

 

 

CYCLE TIME:

01:30

MAIN

 

 

START

-2-

Page 3
Image 3
Traulsen RBC200RT, RBC400RT owner manual By Time, Type Chill, Start