GOLD CGi Gas-Fired Water Boiler — Boiler Manual

1e Prepare boiler location — air openings

Combustion air opening location and sizing requirements depend on the clearances around the boiler. Check the boiler placement compared to

Figure 1a, page 7.

 

 

If all clearances are at least equal to Figure 1a,

 

page 7, apply the sizing and placement of openings

 

given on pages 10 and 11.

 

If ANY clearance is less than Figure 1a, page 7,

 

you must provide air openings sized and located as

 

shown in Figure 1b, page 7. DO NOT apply the sizing

 

and location information shown on page 10 or 11.

Figure 2 Air openings to interior spaces

Figure 3 Air directly through outside wall

Air openings must be provided

Combustion air and ventilation openings must comply the National Fuel Gas Code ANSI Z223.1-latest edition, or applicable local building codes. Canadian installations must comply with B149.1 or B149.2 Installation Codes.

Provide adequate combustion and ventilation air to assure proper combustion and reduce the risk of severe personal injury, death or substantial property damage caused by flue gas spillage and carbon monoxide emissions.

Air opening options

Two openings — Air supply from inside the building

1.If the building is of unusually tight construction (see definition, next page), the building must also be provided with air openings directly to the outside, sized and located per Figure 3, Figure 4 or Figure 5.

2.Buildings of typical construction should provide adequate combustion air from natural infiltration, so additional air openings to the building are not required.

3.See Figure 2. Provide two openings through the interior wall, within 12 inches of the ceiling and the floor, sized per Figure 2.

Figure 4 Air from outdoors — vertical ducts

Two openings — Air supply directly from outside

1.Air openings must be directly through an outside wall, or into a space that connects directly to the outside (such as a ventilated attic or crawl space, for example).

2.See Figure 3 — Openings directly through an outside wall — provide two openings within 12 inches of the ceiling and the floor, sized per Figure 3.

3.See Figure 4 — Air supplied through vertical ducts — provide two openings terminated within 12 inches of the ceiling and the floor, sized per Figure 4.

4.See Figure 5 — Air supplied through horizontal ducts — provide two openings within 12 inches of the floor and the ceiling, sized per Figure 5.

Figure 5 Air from outdoors — horizontal ducts

10

Part Number 550-110-710/0107

 

Page 10
Image 10
Weil-McLain 550-110-710/0107 1e Prepare boiler location air openings, Air openings must be provided, Air opening options