Installation

Wiring - General

The ACCB-L comes with a ground bar only. The ACCB-L-L1 is pre-wired at the factory and ready for connection to one Sine Wave Plus Inverter/Charger. The factory-installed wires are labeled to assist with the installation procedure.

See Figure 2-12 on page 2–17 for an illustration of the ACCB-L-L1.

See Figure 2-13 on page 2–18 for an illustration of the ACCB-L2-PCK installed in the ACCB-L-L1 to create the ACCB-L-L2.

WARNING: Shock Hazard

Any changes to factory wiring must meet local and national electrical codes.

WARNING: Fire Hazard

A possible fire hazard can exist if 120 Vac only sources (such as inverters and generators) are wired incorrectly into 120/240 Vac distribution panels containing multi wire branch circuits. For more information on multi-branch wiring, see the Xantrex website (www.xantrex.com).

WARNING: Shock Hazard

Be sure to connect the ground wires first when connecting AC wiring to prevent a potential shock hazard.

WARNING: Shock Hazard

While installing the components, ensure that no DC or AC voltage is being supplied to the inverter.

Accessing the AC Input/Output Terminal Block in the ACCB-L-L1

Consult the Sine Wave Plus Inverter/Charger Owner’s Manual for additional information on wire and disconnect requirements.

To prepare the ACCB-L-L1 and inverter for wiring installation:

1.Expose the AC Input/Output Terminal Block in the ACCB-L-L1 by removing the front cover, as described on page 2–6.

2.Expose the terminal block in the SW Plus Inverter by removing the AC access cover, as described in your inverter’s owner’s guide.

2–14

973-0031-01-01 Rev A

Page 36
Image 36