SECTION 3
INSTALLATION AND INITIAL TURN-ON
The following table shows acceptable wire gauges to be connected to the
Wire Gauge Table | ||
Termination | Wire Range AWG | |
|
| |
Compression Lug (AC) | Up to 4 | |
Conductors Per Phase | ||
| ||
|
| |
Compression Lug (DC+ and | Up to 8 | |
Conductors for each (+) and | ||
| ||
|
| |
Terminal Block (DC Neutral) | Up to 2 | |
Conductors | ||
| ||
|
|
INSTALLATION INSTRUCTIONS
CAUTION
All wiring methods shall be in accordance with the National Electrical Code ANSI/ NFPA 70. All power conductors interfacing to the
Ventilation Considerations
Maintain a minimum of 12” clearance in back , front and both sides of the
Installation
1.Move the
2.Anchor the lower enclosure feet to the floor with a 1/2” anchor bolts.
3.Install all conduits needed for cable entry in the shaded areas of both AC and DC interface enclo- sures as shown in Figure
DOCUMENT: 151811 | ||
|
Operation and Maintenance Manual
Copyright 2003, Xantrex Technology Inc.