Installation

Installation

 

 

Overview

 

 

Installation steps

There are four main steps in the installation of the Sun Tie XR:

 

1. Mounting the unit

 

2. Making the DC connections from the PV array to the Sun Tie XR

 

3. Making the AC connections from the service utility panel to the

 

Sun Tie XR

 

4. Grounding the PV array

 

This section also discusses two installation options: connecting inverters

 

in parallel and connecting the Remote Monitor.

 

 

 

 

WARNING: FIRE, SHOCK and ENERGY HAZARDS

 

Before installing the Sun Tie XR, read all instructions and

 

cautionary markings located in this manual, on the PV array,

 

and on the main service panel.

Mounting

 

 

 

 

Surfaces for

The Sun Tie XR must be mounted to a flat, vertical surface such as

mounting

wallboard or wood siding. Installation onto wallboard or concrete

 

requires the use of anchors to properly hold the screws.

 

 

 

 

WARNING: SHOCK HAZARD

 

Before drilling holes to mount the Sun Tie XR, ensure there are

 

no electrical wires or plumbing in this area. Since this unit is

 

installed close to the utility entrance or meter, there may be a

 

high concentration of electrical wire in the area.

 

 

 

 

 

 

CAUTION

 

The Sun Tie XR weighs approximately 35 pounds. Always use

 

proper lifting techniques during installation to prevent personal

 

injury.

 

 

 