Main Burner and Orifice Removal

Main Burner and Orifice Removal

1.Remove screws and burner hold down bracket. NOTE: If the heat exchanger is sooted badly, the burner hold-down bracket and spacer can become distorted from direct flame impingement and this usually necessitates replacement of these parts.

2.Lift burners from slotted spacer and slide from ori- fices. Clean with a wire brush.

3.Orifices usually do not need to be replaced. To clean, run either copper wire or wood through ori- fice. Do not enlarge hole. To remove orifice, use a socket wrench and remove the manifold. DO NOT overtighten when reinstalling.

Pilot Removal and Cleaning

1.Disconnect pilot tubing at pilot and sensor/igniter wire. Remove screws holding pilot bracket to burn- er drawer.

2.Remove pilot and bracket, clean pilot of debris, small bugs, etc., with wire or small brush.

3.Replace pilot, pilot tubing, sensor ignition wires and check for leaks.

Heat Exchanger Removal

1.Shut water, gas and electricity off, close valves, relieve pressure and remove relief valve. Remove side inspection panels.

2.Remove top holding screws.

3.Remove draft diverter, lift and remove top and flue collector on stack type models. Remove inspec- tion panels.

4.Loosen bolts and disconnect flange nuts on inlet/outlet header, loosen union(s) at gas pipe, and slide heater away from piping until studs clear the heater.

5.Remove heat exchanger corner brackets.

6.Remove combustion chamber clips at the four cor- ners of the heat exchanger.

7.Lift heat exchanger straight up using caution not to damage refractory.

Heat Exchanger Reassembly

1.Heat exchanger header O-rings should be replaced with new ones.

2.Install inlet-outlet and return water headers and install header retainer nuts and torque nuts even- ly.

3.Install the four (4) corner clips between tube sheets and refractory. Replace "V" baffles.

4.Install thermostat sensing bulbs in header wells and replace bulb retaining clips.

5.Install inlet and return pipes in water headers using pipe thread sealant.

6.Install water pressure relief valve, flow switch, and low water cutoff devices if so equipped.

7.Open water supply and return shutoff valves. Fill heater and water piping system with water. Check heater and piping system for leaks at full line pres- sure. Run system circulating pump for a minimum of 1/2 hour with heater shutoff.

8.Shut down entire system and vent all radiation units and high points in system piping. Check all strainers for debris.

9.Install flue collector, jacket top and inspection pan- els. Install top holding screws. Install draft diverter and vent piping if so equipped.

10.If gas piping was disconnected, reconnect gas pip- ing system and check for leakage using a soap solution.

11.Double check electrical circuits, grounding con- nections and pump with wiring diagram supplied with heater.

12.Check for correct water pressure and water level in the system. Make sure that system pump oper- ates immediately on the call for heat. The system is ready for operation.

28

Image 28
Contents Raytherm Commercial Swimming Pool Heater INSTALLATION & OPERATING INSTRUCTIONSModels P-926to P-1826 & P-2100to P-4001 Corrosive water voids all warranties CONTENTS Pay Attention to These Terms WARNINGSDANGER RECEIVING EQUIPMENT INSTALLATION GENERAL SPECIFICATIONSBase Installation Code RequirementsClearances Combustion Air Indoor Units OnlyIndoor Heaters Outdoor HeatersDrafthood Indoor Models Venting ConnectionsVent Piping Gas Supply Connections Gas Pressure RegulatorVenting of Diaphragm Gas Components Model1-1/4” 1-1/2”CONTROLS Flow SwitchWater Connections Water Pressure Switch Automatic Chlorinators and Chemical FeedersUnitherm Governor Operation Companion Flange Connections ModelsModel No ConnectionMinimum Model No. Loop* Flow Rates Heater Flow2.Lace metal strapping or clamps, NOT PROVID- ED through the ¾” slots on the cover and fasten securely to pipe as shown in Fig. 15 & 16. Do not over-tightenclamps HEATER Models 0926 thru 1223 with UG RECOMMENDED FIELD INSTALLED ISOLATION VALVESFORSERVICEBLENDEDWATER TEMPERATURE THERMOMETERATHEATERINLETModels 2100 thru HEATEROUTLETTEMPERATURETHERMOMETERExternal Auxiliary Bypass Valve Where Required Auxiliary Bypass Valve Adjustment926-1223Models Only Temperature ControlsElectrical Wiring High & Low Gas Pressure SwitchesLow Water Cutoff Electronic IgnitionWiring Diagram-Models Wiring Diagram-Models Wiring Diagram-Models Wiring Diagram-Models Pressure Switch Pressure Switch AdjustmentSERVICING General Location Of ControlsSTART-UP PROCEDURES Pilot SafetyTwo-SpeedPumps Before Start-UpAfter Start-Up INSPECTION PROCEDURESBurners SERVICING PROCEDURES Tube Cleaning Procedure TypicalBurner Drawer Removal Gas Valve RemovalPilot Removal and Cleaning Heat Exchanger ReassemblyMain Burner and Orifice Removal Heat Exchanger RemovalControl Well Replacement Tube Replacement ProcedureProcedure For Cleaning Flue Gas Passageways Combustion Chamber RemovalMAINTENANCE AND CARE Unitherm Governor ReplacementUNITHERM GOVERNOR WITH POWER ELEMENT INLET/OUTLET HEADER OUTLET INLET GASKETWinterizing Your Heater MECHANICAL FOR QUALIFIED SERVICE PERSONNEL ONLY TROUBLESHOOTINGIMPORTANT NOTICE or refer to heater sizing chart Reset time clockClean filter Refer to installation instructionsTROUBLESHOOTING HONEYWELL S8600 Intermittent Pilot SystemELECTRICAL ELECTRONIC IGNITION IID IID STARTLIMITED WARRANTY RAYTHERM TYPE P SIZES HEAT EXCHANGER WARRANTYADDITIONAL WARRANTY EXCLUSIONS PARTS REPLACEMENT