You must perform the following before operating the system:
•If generator is installed in an area regularly subjected to temperatures below 40°F (4°C), select a 50 second warm up time by moving jumper installed on JP2 from ‘20’ position to ‘50’ position.
•Place the 2 position sliding switch on the control module in the NG or LP position, whichever is appropriate for your system.
•Place the 3 position sliding switch on the control module to match the KW rating of the Home Standby Generator set.
3 Position |
| 2 Position |
Switch | JP2 | Switch |
CT1 & CT2
Connectors
Supervisory
Contacts
Controls
The Manual Override lever is to be used only by licensed professionals. The essential branch circuit breakers are used in the same way as those supplied in the main distribution panel.
Operation
To select automatic transfer operation, do the following:
1.Set essential circuit breaker that sends utility power to transfer switch to “On” position.
2.Set generator’s main circuit breaker to its “On” position.
3.Install 15 Amp fuse in control panel on generator.
4A. If generator is equipped with a system ON/OFF switch, set switch to “ON” position.
B.If generator is equipped with a AUTO/OFF/MANUAL switch, set switch to “AUTO” position.
The system will now be in automatic operation mode.
When the generator is providing power to the transfer switch, the controller is constantly monitoring generator power. If the air conditioner is called to run, and there is sufficient generator power available, the controller will close contacts
Testing the Automatic Transfer Switch
Turn the essential circuit breaker feeding the transfer switch to the “Off” position. The automatic sequence will follow. To go back to utility power, turn the essential circuit breaker to the “On” position.
Utility Fail
The Home Standby Generator set senses when utility voltage is below 70 percent of nominal. Engine start sequence is initiated after 6 second time delay.
Engine Warm-Up
Time delay to allow for engine
Transfer
Transfer from utility to generator supply occurs after voltage is above set levels. Minimum engine run time is 5 minutes after transfer.
Utility Pickup
Voltage pickup level is 80 percent of nominal voltage.
Retransfer
Retransfer from generator to utility supply is approximately 10 seconds after utility voltage supply is above pickup level and minimum run time is completed.
Engine Cool Down
Engine will run for 60 seconds after retransfer.