3. Insert the pins in the front bracket into cabinet holes 22 and 33 (FIGURE 1-6).

Front bracket

 

secured to outer cabinet holes

Adjustable bracket

 

 

secured to inner cabinet holes

FIGURE 1-6Installing the Slide Rails in a Sun Fire Cabinet

The pins hold the bracket in place until the bracket is secured.

4.Secure the adjustable bracket into cabinet holes 24 and 31 with two No. 10-32 UNF screws.

5.Secure the front bracket into cabinet holes 24 and 31 with two No. 10-32 UNF screws.

6.Repeat Step 1 through Step 5 for the second slide rail assembly.

Note – Mounting the server in cabinet holes 24 and 31 allows for 10-inches of space beneath the server in order to service the backplane.

To Install the Slide Rail Assemblies in the Top Position

1.Adjust the position of the adjustable bracket on each slide rail assembly.

a.Loosen the two nuts that secure the adjustable bracket.

b.Reposition the adjustable bracket to the location stamped “SUNFIRE” on the rear bracket and secure the adjustable bracket.

2.Adjust the length of each slide rail assembly.

10 Netra 1290 Server Installation Guide • May 2006

Image 22
Contents Netra 1290 Server Installation Guide Please Recycle Contents Setting Up 39 Setup Process Netra 1290 Server ConnectionsFigures System Controller and I/O Assembly Locations Tables Viii Netra 1290 Server Installation Guide May Using Unix Commands How This Document Is OrganizedShell Prompts Typographic ConventionsDocumentation, Support, and Training Related DocumentationThird-Party Web Sites Sun Welcomes Your Comments Unpacking the Server To Unpack the ServerRemove and unpack the shipping kit 1Opening the Shipping CartonRemove the outer carton 2Removing the Carton PiecesInstalling Slide Rails Remove the internal saddleAdjusting the Slide Rail Assembly N F I R ETo Install the Inner Rails on the Server Spring clip should engage To Prepare the Rails for 2-Post Installations Repeat through for the second inner railTo Install the Slide Rail Assemblies in the Bottom Position To Install the Slide Rail Assemblies in the Top Position To Install the Slide Rail Assemblies in the Bottom Position Front bracket Rear bracket Secured to outer cabinet holes To Install the Slide Rail Assemblies in the Top Position Netra 1290 Server Installation Guide May To Prepare to Install the Server in the Cabinet Installing the Server in a CabinetSecure the front bracket with two No -32 UNF screws Repeat Step a and Step b for the second front bezel door Remove the shipping cradle bolts FigureTo Mount the Server in the Cabinet 9Removing the Shipping Cradle BoltsLatches on each side must click out, locking the rails Outer rails Inner rails 12Removing the Shipping Cradle Retract the cabinet stabilization mechanism as required 13Pushing the Server Into the System CabinetTo Install the Lock Nuts Installing Slide Rail Lock NutsReattach the front doors of the server Slide the server into the system cabinet 15Inserting and Tightening the SpacersInstalling the Cable Management Arm To Install the CMA-Lite on To Install the CMA-800 onTo Install the CMA-Lite 18CMA-Lite Cable Management ArmTo Install the CMA-800 20Upper and Lower Pivot Bracket Mounting Holes Hinge pin Upper pivot bracket Upper CMA arm Hinge pin Lower pivot bracket Lower CMA arm Slide rail Left hand T-bracket Slide rail Right hand T-bracket 25Attaching the Upper and Lower CMA Arms to the T-Bracket Connecting Power Cables To Connect the Power CablesConnecting Consoles to the System Controller To Connect the Initial Administrative Console Set up the system consoleTo Connect the Administrative Console Set up the chosen administrative consoleInstalling Additional Hardware Connecting the I/O AssembliesTo Connect the I/O Assemblies Installing Additional Peripheral Devices Setting Up Setup ProcessOn/Standby Switch Setting Up the HardwareTo Install and Cable the Hardware To Power On Using the On/Standby Switch Powering On the ServerDisabling Operation of the On/Standby Switch To disable the On/Standby switch, use the setupsc commandTo Power On Using the LOM poweron Command Bringing the Server to Standby ModeAt the lom prompt, type Press the left side of the system On/Standby switch To Bring the System to Standby Mode From the LOM PortFor an abrupt power off, type At the system prompt, typeAt the LOM prompt, type the SC password command Setting Up the ServerTo Set Up the Password To Set the Date and TimeAt the LOM prompt, type setupnetwork To Configure Network ParametersAnswer the questions in the script To Install and Boot the Solaris Operating System Installing and Booting the Solaris Operating SystemAccess the LOM prompt To power on the server, type poweron Installing the Lights Out Management PackagesIf necessary, install the Solaris Operating System To Install the LOM Drivers As superuser, type’type=ddipseudoname=lomp To Install the LOM Utility To Install the LOM Manual Pages# pkgadd -d . SUNWlomm Netra 1290 Server Installation Guide May Netra 1290 Server Connections External I/O Connection LocationsPCI+ Ibssc Assemblies Figure A-1External I/O Connection LocationsScsi Connector SCSI3Alarms Port Scsi ImplementationTable A-3Alarms Service Port Connector Pinout NET0/NET1 Ethernet Ports10/100BASE-T LOM Ethernet Port NETLOM Serial a and Serial B Ports Twisted-Pair Ethernet Cable-Type ConnectivityLOM Serial a Serial B Using a DB-25 Adapter for Your Serial Link Using a DB-9 Adapter for Your Serial LinkNetra 1290 Server Installation Guide May Index Setupnetwork command