Marathon Computer V-4224 installation manual General Installation

Page 28

3 INSTALLATION

GENERAL INSTALLATION

CAUTION:

Review this manual before beginning the installation. Study the jobsite and installation requirements carefully to be certain all necessary safeguards and/or safety devices are provided to protect all personnel and equipment during the installation and as a completed system.

These instructions are not intended as a substitute for training and experience in proper use, safety procedures, maintenance, or installation of this equipment.

This baler is designed for INDOOR USE ONLY.

Marathon does not assume responsibility for the installation procedures of this equipment. Conformance to applicable local, state, and federal laws concerning installation rests with the customer.

DECALS

Installation of the baler is not complete until an inspection of the warning decals has been made. Decals should be clearly visible, legible, securely applied, and in the proper location. For decal description and location, see DECALS and DECAL PLACEMENT in Section 1, pages 10 & 11.

DANGER: DO NOT CLIMB ON SIDES OF BALER. USE A LADDER OR WORK PLATFORM WHEN WORKING ON TOP OF THE BALER OR OTHER AREAS OF THE BALER THAT CAN NOT BE REACHED FROM GROUND LEVEL.

WARNING: PA RTS OF THE FEED GATE WILL EXTEND ABOVE THE TOP OF THE BALER WHEN THE FEED GATE IS FULLY RAISED.

3-1

Image 28
Contents Play IT Safe VERNON, AL FAYETTE, AL YERINGTON, NV CLEARFIELD, PAContents Operation EC Declaration of Conformity Stand Clear While Baler is in Operation PRE-OPERATING InstructionsControls ON-OFF Keyed Selector Switch Control DescriptionOperating Instructions Making a Bale To Make a BaleOperating Instructions Bale TIE OFF/BALE Eject For Bale TIE OFF & Bale EjectDiagram Bale TIE OFF/BALE Eject Front View of BalerSide View BaleTIE Slot Cleaning Slot Cleaning Tool Front ViewDecals Decal Placement 460400 Supporting of Platen Periodic Maintenance Annual Filter MaintenanceMonthly Three MonthsPressure Setting Hydraulic System Pressure SettingPressure Setting and Interlock Testing Magnetic Interlock TestingCylinder Removal Cylinder Removal and RebuildingCylinder Rebuilding Feed Gate Latch Adjustment Operating Characteristics Principles of OperationCharts Electrical Requirements VoltagePanel BOX Power Unit Electrical Schematic Hydraulic Schematic 0489Parts List Recommended OilsInstallation General InstallationAnchoring to Concrete PAD Electrical Installation Grounding InstructionsMotor Rotation Applies to Three Phase Units only START-UP Instructions