Vanguard Managed Solutions 6500 PLUS Installation, Procedure, Step Action Description/Result

Page 29

Installing Standalone Units

Installation

The standalone enclosure already contains a 6505PLUS, 6507PLUS, or 6525PLUS card.

 

Procedure

To install the unit, follow these steps:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Step

 

 

 

 

Action

 

Description/Result

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1

Place the unit at its designated site

The power cord is attached to the

 

 

 

 

and plug the power cord into a

back of the unit (Figure 2-2).

 

 

 

 

suitable primary power source.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2

Switch on the power, located at the

The front panel lights turn on

 

 

 

 

rear of the unit.

 

as described in the “Power-Up

 

 

 

 

 

 

 

 

 

 

Verification” section on

 

 

 

 

 

 

 

 

 

 

page 2-74.

 

 

 

 

 

 

 

 

 

 

After a few minutes, the green

 

 

 

 

 

 

 

 

 

 

STATUS light comes on to indicate

 

 

 

 

 

 

 

 

 

 

the node is ready to process calls.

 

 

 

 

 

 

 

 

 

 

If this does not occur, call your

 

 

 

 

 

 

 

 

 

 

VanguardMS representative.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3

Configure the unit through the

To access the CTP, attach a

 

 

 

 

Control Terminal Port (CTP)

 

terminal to Port 6 with an EIA

 

 

 

 

menus.

 

232-D connector. Port 6’s default

 

 

 

 

 

 

 

 

 

 

settings are standard terminal port

 

 

 

 

 

 

 

 

 

 

values: 9600 baud, 8 data bits, 1

 

 

 

 

 

 

 

 

 

 

stop bit, no parity.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4

When the (*) prompt appears on

This is the default password value.

 

 

 

 

the terminal, type the following:

The Main menu appears. See the

 

 

 

 

.ctp <CR>

 

Vanguard ONS Basics Protocols

 

 

 

 

At the password prompt, press

Manual (T0106) for configuration

 

 

 

 

<CR>

 

information.

 

Rear View

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 2-2shows the rear view of the standalone enclosure.

 

 

..

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PORT 6

PORT 5

PORT 4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PORT 3

PORT 2

PORT 1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 2-2. Rear View of Standalone Enclosure

Installation

2-21

Image 29
Contents Vanguard Managed Solutions Restricted Rights Legend Restricted Rights Notification for U.S. Government UsersRadio Frequency Interference Regulations Proprietary MaterialPage Contents Contents This Chapter Describes About This ManualOverview Level Mise en gardeChapter Protocols Software FeaturesFeatures Card Types HardwareProcessor Cards Support CardsEnclosure Enclosures and BackplanesStandalone VanguardMS Supports OtherProducts Types of Modulus6500PLUS Processor Cards 6525PLUS Network ConfigurationsConcentrator PortPlus Processor Card Front Panel Hardware 6500PLUS Auxiliary Processor Cards AIO Card 6500PLUS Asynchronous and Universal I/O CardsUIO Card Card Type Works with Port Types Split SpeedPlus Universal I/O or Asynchronous I/O Card Front Panel NSO Card 6500PLUS Network Storage Option CardPlus Network Storage Option Card Token Ring Interface Module Trim Card 6500PLUS Token Ring Interface Module OptionHardware Hardware 6500PLUS Integral DSUComponents DSU InterfacePage Chapter Installation OverviewUnpacking Installing Standalone UnitsSite Preparation ExampleProcedure InstallationStep Action Description/Result Rear ViewStep Action Replacing Processor Cards in Standalone EnclosuresRemove the Standalone Enclosure Door Bottom of Standalone Enclosure Locking Tabs Using Screwdriver on Locking TabsPlus Processor Card with Retaining Screw Replacement CardStep Action Information Installing Nodes in Modulus EnclosuresAdditional Multiprocessor Multiprocessor NodesNode Example OperationAction Result/Description Replacing Master Processor of Multi-Processor NodeInstalling Nodes in Modulus Enclosures Step Action Result/Description When To Add Another Processor with Flash Before You BeginAdding a Secondary 6500PLUS Processor with Flash Maintaining Select Enable FlashCurrent Software RevisionSelect Copy Software to Flash Upgrading with Software From the New Processor CardModulus 8/18 Installing/Replacing Processor CardsProduct Description Code Requirements for Installing a Trim CardTrim Card Rear Filler Panel for Modulus 8/18 Enclosures Guidelines for Installing a Trim Card in a Modulus 8/18 Trim Card Spacing in a Modulus 18 Enclosure 10. Trim Card Rear Filler Panel for Modulus 9/21 Enclosures Installing Nodes in Modulus Enclosures 11. Trim Card In Left-most Position of Modulus 21 Enclosure Plus Between Two BackplanesEnclosure Installing Nodes in Modulus Enclosures Attaching a Trim Card Installing and Connecting a Trim CardConnecting a Trim Card InstallingCables AttachingBefore Removing Removing/Replacing Trim CardsTrim Cards TRIM/Processor CardModulus 18 with Preparing Modulus Enclosures for RFI SuppressionSuppression Installing RFIScreen Modulus 18 RFI15. RFI Suppression Straps Modulus 18 No Trim Card No Trim CardBar Modulus 21RFI Suppression Ctp CR Starting Up the NodeNode Startup Processor Card Replacing Processor Card ComponentsReplacing DIMs New DIM RemovalJumpers 19. Jumpers on the Port Interface Pins20. Installing Jumpers on the Port Interface Pins Guidelines Installing SIMMs21. Simm Installation Replacing Flash Modules 22. Flash Module Installation Module Replacing ID ModulesChips Replacing Prom ChipsReplacing the Cmem Chip Installing the DSU DSU DIM InstallationControl Terminal Configuring the 6500PLUS for DSU Operation Output Signals DSU Input and Output SignalingInput Signals Loopback Options 24. Diagnostics MenuTroubleshooting Troubleshooting DSU DIM InstallationFacility Interface DSU DIM FCC InformationType of Interface DSU DIM Installation Checking Power-Up VerificationLights Event Result/DescriptionDiagnostics Power-UpNode Setting Node to Default ConfigurationInstalling Software Options Access Serial Accessing Node Serial Number from Node StatisticsNumber Status/Statistics Select Node Stat25. Serial Number on Node Stat Screen Configure Select Software Key Table Enabling a Software Access KeyFollow These StepsInstall New Installing New Software Options in an Existing NetworkEnhanced LAN Option Cables Appendix aFunction/Signal Function/Signal PinPin Name Position35/V.36 Modulus 9/21 Enclosures Position Signal NameFunction Pin FunctionSignals Modulus 9/21 Enclosures 35/V.36 Signals Standalone and Modulus 8/18 Enclosures Position Name Signals Standalone and Modulus 8/18 EnclosuresPin Function Page Unit Dimensions SpecificationsPhysical Characteristics Limits Power RequirementsEnvironmental DIM IndexLL 2-69RS