American Power Conversion 60kW InfraStruXureTM System manual Space Considerations

Page 14

Space Considerations

Study the figure below to determine your space requirements for installing the InfraStruXure PDU. Consult your local codes and the NEC for additional requirements.

Ceiling Clearance

123>12in (304mm)

 

Minimum Rear Clearance

 

208V: 36in (914mm)

Minimum Front Clearance

480V: 42in (1067mm)

 

208V: 36in (914mm)

 

480V: 42in (1067mm)

6

InfraStruXure System—Installation and Start-Up

Image 14
Contents Installation and Start-Up Page About this Manual Page Contents Start-Up Procedure Appendix a Operation Page Overview Safety symbols used in this manualCross-reference symbols used in this manual Installation/Maintenance Receiving/moving Total Power Off Emergency Power Off EPOPage NetShelter VX Enclosure DimensionsInfraStruXure PDU Space Considerations Weight Considerations Component Maximum WeightHeat Output Electrical requirements Electrical Requirements and SpecificationsProcedures requiring a licensed electrician 208V Input 480V Input 600V InputEmergency Power Off EPO OverviewBasic Installation Procedure Licensed electrician must connect the power sourceSite Planning Basic Installation Procedure Installation Procedures Level the PDU and NetShelter EnclosuresAttach conduit to the PDU for the input conductors Connect the Power Source to the PDUAccess the PDU Main Input switch Installation Procedures Connect the Power Source to the PDU Terminal Torque Tools Install a circuit breakerTorque specs and tools required Connect input conductors 208V input without a transformerConnect an Emergency Power Off Switch Contact closure 24VAC 24VDC Contact closure is recommended24VAC/VDC-Normally Open Contact Closure-Normally OpenContact Closure-Normally Closed Problem Action Safety warnings Overview How to connect contacts to the PDU Monitoring Unit Relay output specifications990-1393B Cable Ladders for overhead wiring across rows Install the Rack Power Distribution Units PDU Install InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches ATS Install the InfraStruXure Manager and Hub or SwitchRoute and Attach Overhead Wiring Route and attach power cables to equipment racksInstallation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Wiring Under the Floor Installation Procedures Wiring Under the Floor Route Data Cables to the InfraStruXure Manager Hub or Switch Start-Up Procedure Ensure that all power is offApply power to the system Start-Up Procedure InfraStruXure System Configure the InfraStruXure Manager How to Apply Power to the System Appendix a OperationDistribution panel circuit breakers How to Ensure Total Power Off For PDU with transformer Set the MainPage General changes Changes by page numberPage Index InfraStruXure System-Installation and Start-Up Page Page Page Page Page Page Page 990-1638B