American Power Conversion 60kW InfraStruXureTM System manual Start-Up Procedure

Page 41

Start-Up Procedure

Safety warnings

This section provides instructions on how to perform a system start-up. Do not skip any steps in this procedure.

Only APC Field Service Engineers or qualified, APC-trained personnel may perform a system start-up.

Electrical

Hazard

Before you proceed, ensure that power is off by following the procedure in this section.

Electrical

Hazard

Ensure that all power is off

1. Set the PDU Main Input to OFF.

2. Set the upstream input circuit breaker (utility or UPS) to the OFF or Locked Out position.

InfraStruXure System—Installation and Start-Up

33

Image 41
Contents Installation and Start-Up Page About this Manual Page Contents Start-Up Procedure Appendix a Operation Page Overview Safety symbols used in this manualCross-reference symbols used in this manual Receiving/moving Installation/MaintenanceEmergency Power Off EPO Total Power OffPage NetShelter VX Enclosure DimensionsInfraStruXure PDU Space Considerations Component Maximum Weight Weight ConsiderationsHeat Output Procedures requiring a licensed electrician Electrical Requirements and SpecificationsElectrical requirements 208V Input 480V Input 600V InputOverview Emergency Power Off EPOLicensed electrician must connect the power source Basic Installation ProcedureSite Planning Basic Installation Procedure Level the PDU and NetShelter Enclosures Installation ProceduresAttach conduit to the PDU for the input conductors Connect the Power Source to the PDUAccess the PDU Main Input switch Installation Procedures Connect the Power Source to the PDU Terminal Torque Tools Install a circuit breakerTorque specs and tools required 208V input without a transformer Connect input conductorsContact closure 24VAC 24VDC Contact closure is recommended Connect an Emergency Power Off Switch24VAC/VDC-Normally Open Contact Closure-Normally OpenContact Closure-Normally Closed Problem Action Safety warnings Overview Relay output specifications How to connect contacts to the PDU Monitoring Unit990-1393B Cable Ladders for overhead wiring across rows Install the Rack Automatic Transfer Switches ATS Install InfraStruXure Rack-Mount DevicesInstall the Rack Power Distribution Units PDU Install the InfraStruXure Manager and Hub or SwitchRoute and attach power cables to equipment racks Route and Attach Overhead WiringInstallation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Wiring Under the Floor Installation Procedures Wiring Under the Floor Route Data Cables to the InfraStruXure Manager Hub or Switch Ensure that all power is off Start-Up ProcedureApply power to the system Start-Up Procedure InfraStruXure System Configure the InfraStruXure Manager Appendix a Operation How to Apply Power to the SystemDistribution panel circuit breakers For PDU with transformer Set the Main How to Ensure Total Power OffPage Changes by page number General changesPage Index InfraStruXure System-Installation and Start-Up Page Page Page Page Page Page Page 990-1638B