Start-Up Procedure: InfraStruXure System
Apply power to the system
1. Set the upstream input circuit breaker (utility or UPS) to ON.
2.Ensure A-B-C clockwise phase rotation at the top of the Main Input on the PDU, using a phase rotation meter.
3.Set the Main Input on the PDU to ON.
4.Verify A-B-C clockwise phase rotation at the top of the primary winding of the transformer, using a phase rotation meter.
5.Verify that the proper voltage is present on the secondary winding of the transformer (208V, metered phase-to-phase), using a true RMS voltmeter.