American Power Conversion 60kW InfraStruXureTM System manual Heat Output

Page 16

Heat Output

Consider the heat dissipation ratings of equipment to determine cooling requirements. Additional cooling equipment may be required. Heat output of the InfraStruXure PDU is shown below.

 

Voltage

 

 

 

 

InfraStruXure PDU with a transformer

208V input

7169 BTU/hr

 

 

(2.10kW)

 

480V input

7412 BTU/hr

 

 

(2.17kW)

 

600V input

4894 BTU/hr

 

 

(1.43kW)

 

 

 

The heat output is higher while batteries are charging. Under normal operating conditions, battery recharging periods are infrequent.

Note

8

InfraStruXure System—Installation and Start-Up

Image 16
Contents Installation and Start-Up Page About this Manual Page Contents Start-Up Procedure Appendix a Operation Page Cross-reference symbols used in this manual Safety symbols used in this manualOverview Installation/Maintenance Receiving/movingTotal Power Off Emergency Power Off EPOPage InfraStruXure PDU Dimensions NetShelter VX Enclosure Space Considerations Weight Considerations Component Maximum WeightHeat Output Electrical Requirements and Specifications Procedures requiring a licensed electricianElectrical requirements 208V Input 480V Input 600V InputEmergency Power Off EPO OverviewBasic Installation Procedure Licensed electrician must connect the power sourceSite Planning Basic Installation Procedure Installation Procedures Level the PDU and NetShelter EnclosuresAccess the PDU Main Input switch Connect the Power Source to the PDUAttach conduit to the PDU for the input conductors Installation Procedures Connect the Power Source to the PDU Torque specs and tools required Install a circuit breakerTerminal Torque Tools Connect input conductors 208V input without a transformerConnect an Emergency Power Off Switch Contact closure 24VAC 24VDC Contact closure is recommendedContact Closure-Normally Closed Contact Closure-Normally Open24VAC/VDC-Normally Open Problem Action Safety warnings Overview How to connect contacts to the PDU Monitoring Unit Relay output specifications990-1393B Cable Ladders for overhead wiring across rows Install InfraStruXure Rack-Mount Devices Install the Rack Automatic Transfer Switches ATSInstall the Rack Power Distribution Units PDU Install the InfraStruXure Manager and Hub or SwitchRoute and Attach Overhead Wiring Route and attach power cables to equipment racksInstallation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Wiring Under the Floor Installation Procedures Wiring Under the Floor Route Data Cables to the InfraStruXure Manager Hub or Switch Start-Up Procedure Ensure that all power is offApply power to the system Start-Up Procedure InfraStruXure System Configure the InfraStruXure Manager How to Apply Power to the System Appendix a OperationDistribution panel circuit breakers How to Ensure Total Power Off For PDU with transformer Set the MainPage General changes Changes by page numberPage Index InfraStruXure System-Installation and Start-Up Page Page Page Page Page Page Page 990-1638B