Toshiba G8000 Grounding Configuration, Jumper Cable Between the Neutral Terminal & Ground BUS

Page 44

11.5Grounding Configuration

This section describes the grounding configuration to be used with this UPS.

A 2 AWG (or 38 mm2) factory-installeded jumper cable is provided between the neutral terminal and ground bus in the UPS cabinet. The jumper cable location is illustrated below.

100-150 kVA

 

 

Neutral

Ground

Terminal

Bus

 

 

 

Jumper

 

 

 

 

 

 

 

 

Cable

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FIGURE 11.9 - JUMPER CABLE BETWEEN THE NEUTRAL TERMINAL & GROUND BUS

Since the input source is a delta-connection (3-phase 3-wire) without ground, the neutral terminal in the UPS cabinet must be connected to the ground bus with the internal jumper cable as shown in Figure 11.9.

The jumper cable should stay in place. See Figure 11.9 for the jumper cable location.

UPS Cabinet

Input Source

3f

3f

G

3f

3f

G

3 f

3 f

 

N

To

N

G

G

LOAD

 

 

Junper Cable

 

 

remains in place

 

FIGURE 11.10 - GROUNDING CONFIGURATION FOR NON-GROUNDED DELTA-INPUT

36

G8000 Series with Isolated Output Installation and Operation Manual

Image 44
Contents G8000 Series Page G8000 Series Qualified Personnel only Uninterruptible Power System UPS Purpose Toshiba’s Customer Support CenterToshiba Customer Support Center Toshiba International CorporationTable of Contents Terminal Blocks, Terminal Bus, and Power Cables 11.3 Introduction Prohibited Symbol indicates do not take action General Safety InstructionsSymbols Signal Words Qualified PersonnelImportant Safety Instructions Factory Authorized PersonnelSafety Precautions DisclaimerGeneral Maintenance Keep the area arround the UPS cleanTransporting/Unpacking Do not tilt the UPS more than 10 from upright positionDo not transport, move, store, or place the UPS on its side Avoid vibration or shock exceeding 0.5GInspection/Storage Keep the Specified Clearance around the UPS Installation PrecautionsInstall the UPS in a controlled environment Do not install the UPS where water may fall on it Do not block air ventsInstallation Precautions Environment standardPage Wiring/Connection Perform wiring and connections with correct polarityConnect only one 1 ground wire to the earth ground terminal Follow the torque criteria for tightening screwsFor 100 and 150 kVA GND 150kVA UPS Warning Labels Weight and Dimensions Model Unit Shipping150kVA UPS Exterior Dimensions Inches Transporting Do not expose the unit to vibration or shock exceeding 0.5GTransporting By Crane 8.5 show examples of acceptable and unacceptable operationsTransporting By Forklift Transporting UPS by ForkliftOperating Precautions Storage/Operating EnvironmentPage Qualified Personnel shall Maintenance PrecautionsQualified Personnel only Do not open or mutilate the batteries DisposalDo not dispose of the batteries in a fire Installation Unpacking UPS ClearanceAnchor Bolts UPS Wiring BreakerTerminal Blocks, Terminal Bus, and Power Cables AC Input Bypass Input AC Output BatteryBlock Number Cable Size Tightening Torque 100 KVA 150 KVA External Breakers Bottom Cable Knockout Plates 100 kVAGrounding Wire Be sure to ground the UPS as specifiedControl Wires Signal Name OperationConnection Between UPS, Battery Cabinet & Bypass Breaker Grounding Configuration Jumper Cable Between the Neutral Terminal & Ground BUSMechanical Specification UPS SpecificationsGeneral Specification Rated Capacity 150kVA Electrical Specification Do not open the front coverOperator Interface UPS may not respond if the button press is too shortKey-Switch and Buttons Graphic display Panel KEY-SWITCH/OPERATING Buttons13.2 LCD/LED Indicators Graphic display Panel LCD/LED INDICAtorsLCD Indicators Name DescriptionNormal Display AC-VO AC- I O 50%Volt Freq .0Hz 50%AC I/P-V Freq .0Hz BYP I/P-V Freq .0HzDC-V BATT-V BATT- I 0A 32TIMFault Display 09-09-06LCD Scroll AbbreveationsEpo and Control Power supply operating switches Operating the UPSPerform the pre-operational check before operating the UPS Operation TypesPre-operational Check Startup Procedures StepAC Vo 208 AC Io 50% Switch Power Supply UPS→Bypass Bypass LED is onStop Complete Shutdown DC-V 0 BATT-V 0 BATT-I 0 aChanging Between Float Charge and Equalize Charge Make sure that the Float Charge LED is onMake sure that the Batt FAULT1 warning goes away Types of Errors TroubleshootingEmergency Power Off EPO Faults and Warnings Data Screen 09-09-06LCD Fault & Warning Displays Fault DisplayFault Messages Over HeatAC O/P UV LCD Scroll w/ faults or warnings Button functionsContact Toshiba in the event of malfunction or fault Restoring UPS OperationDo not attempt to modify or relocate the UPS Do not open the front and/or rear panelsPage Page Industrial Division