Chapter 8: Installation verification
This chapter provides the following information about how to verify the server installation and configuration:
●Testing the IPSI circuit packs
●Testing the license file
●Checking LED status indicators
-Servers
-Avaya Ethernet switches
-Uninterruptible power supplies (UPSs)
-Circuit packs
Testing the IPSI circuit pack
The following steps test the clock and packet interface components within the TN2312BP IPSI circuit pack.
Note:
With duplicated servers, use the active server.
1.In a SAT command line, type test
2.Verify that the Test Results screen shows PASS in the Results column.
Testing the license file
! Important:
Wait at least 30 minutes after you install the Communication Manager license before you run this test.
Note:
With duplicated servers, use the active server.
1.On a SAT command line, type test license and press Enter.
2.Verify that the Test Results screen shows PASS in the Results column.