Steam Damper Air Piston (Flow Control) Operation Adjustment

Damper operation was tested and adjusted prior to shipping at 80 psi (5.51 bar). If damper air adjustment is necessary, locate the flow control valve and make the necessary adjustments as noted below.

PREPARATION FOR OPERATION/START-UP

The following items should be checked before attempting to operate the dryer:

Read ALLCAUTION,” “WARNING,” and “DIRECTION” labels attached to the dryer.

Check incoming supply voltage to be sure that it is the same as indicated on the dryer data label.

GAS MODELS - check to ensure that the dryer is

connected to the type of heat/gas indicated on the dryer data label.

GAS AND ELECTRIC MODELS - the sail switch

damper assembly was installed and adjusted at the factory prior to shipping. However, each sail switch adjustment must be checked to ensure that this important safety control is functioning.

Check bolts, nuts, screws, terminals, and fittings for tightness.

GAS MODELS - be sure that ALL gas shutoff valves are in the open position.

Check ALL back guard panels and service box covers have been replaced.

Make sure the lint coop support bracket has been removed.

Check the lint door to ensure that it is closed and secured in place.

IMPORTANT:

!If during installation the lint door safety chain was disconnected, it must be reconnected or personal injury may result.

Rotate the basket (tumbler/drum) by hand to be sure it moves freely.

Check bolts, nuts, screws, terminals, and fittings for security.

STEAM MODELS - check to ensure that a clean,

dry, and regulated air supply (80 psi [5.51 bar]) is on the dryer (with air-operated damper system only).

STEAM MODELS - check to ensure ALL steam shutoff valves are open.

STEAM MODELS - check steam damper operation.

Check basket (tumbler) bearing setscrews to ensure that they are ALL tight.

PREOPERATIONAL TESTS

ALL dryers are thoroughly tested and inspected before leaving the factory. However, a preoperational test should be performed before the dryer is publicly used. It is possible that adjustments have changed in transit or due to marginal location (installation) conditions.

Turn on electrical power to the dryer.

Refer to the Operating Instructions for starting your particular model dryer.

16

American Dryer Corp.

113243-1

Image 18
Contents AD-15 Phase Installation Manual ADC Part NoRetain This Manual In a Safe Place For Future Reference Date of Purchase Model no RESELLER’S Name Serial NumbersTable of Contents Safety Precautions What to do if YOU Smell GASLatest Edition Specifications FIPInstallation Procedures UNPACKING/SETTING UPLocation Requirements Dryer Enclosure Requirements Fresh AIR Supply RequirementsExhaust Requirements Single Dryer Venting Horizontal VentingIllus. a Vertical Venting Illus. B Illus. CMultiple Dryer Common Venting Important Venting Reminders Electrical InformationGas and Steam Models Only GroundingElectrical Connections KLWHRU5HGFor 110V Applications For 208-230/240V Applications GAS Information Gas SupplyNever Test for Leaks with a Flame Steam InformationVoid the Warranty 1RUPDO 0LQLPXP6XSSO\0DLPXP6XSSO\ GAS and Electric Models the sail switch Preparation for OPERATION/START-UPPreoperational Tests GAS and Electric Models only Sail Switch Basket Tumbler CoatingPreoperational Instructions Reversing Timer SPIN/DWELL Adjustments MIN RemainSERVICE/PARTS Information Warranty InformationRoutine Maintenance CleaningSuggested Cleaning Schedule Data Label Information Procedure for 113243-1 Manual Reset Burner HI-LIMIT Instructions PhaseDual Timer Installation Before YOU Start Check Local Codes and PermitsOptional Manual Bypass NON-COIN CoinF.E. System Diagnostics Messages F.E. System Parts Break DownADC 113243 1 2/03/04