Schneider Electric PM5300 manual About Alarms, Second Alarms

Page 63

PowerLogic™ PM5300 series user guide

Chapter 7—Alarms

Chapter 7—Alarms

This section describes the alarm features on PM5300 series Power and Energy meters.

About Alarms

The ! icon appears in the upper-right corner of the meter display when an alarm is active.

If the energy/alarm LED has been configured for alarms, the energy/alarm LED flashes when an alarm is active. See “Alarm / energy pulsing LED setup” on page 60 for more information.

The power meter maintains a counter for each alarm to help keep track of the total number of occurrences (see Figure 7–1).

Figure 7–1: Alarm Counters

If you make changes to the basic power meter setup, all alarms are disabled to prevent undesired alarm operation. Confirm alarm configuration and enable required alarms.

NOTE: Only alarms that apply to the selected power system configuration can be enabled.

The available alarms for this power meter are described in the following sections.

1-Second Alarms

The power meter has 29 standard 1-second over/under alarms. See Table 7–1for a complete list.

Use the display to configure 1-second alarms with the following values:

Enable—disable (default) or enable

Pickup Setpoint (magnitude)

Pickup Time Delay (in seconds)

© 2014 Schneider Electric All Rights Reserved

63

Image 63
Contents PowerLogic PM5300 Series Power and Energy Meter Page Please note Important InformationPage Introduction Chapter Safety Precau Tions EnceHardware Refer Chapter Input / Output Chapter AlarmsChapter Multi-tariff feature Chapter Power qualityChapter Verifying accura Chapter Meter resetsChapter Maintenance UpgradesPowerLogic PM5300 series user guide Introduction Power and Energy Meter HardwareParts and Accessories Box ContentsPowerLogic PM5300 user guide Before You Begin Safety PrecautionsPowerLogic PM5300 series user guide Functions and Characteristics Models, Features and OptionsFunctions and Characteristics PM5300 Series Models, Features and OptionsOther Measurements Power Quality MeasurementsEnergy Values Demand ValuesElectrical Characteristics Technical SpecificationsElectromagnetic Compatibility Mechanical CharacteristicsEnvironmental Characteristics SafetySafety precautions DimensionHuman Machine Interface Mounting the PM5300 Meter mountingMeter wiring Screw driver type M3 Serial No Description SpecificationMake Part code Description Recommended cablesWiring Diagrams Direct connect voltage limits Power systemSymbol Description Current Transformer Voltage disconnect switchPower system setup parameters Power system description Meter settingSymbol Direct connect maximum Voltage and current input wiringVoltage input protection Current input protectionSerial communications Control power wiringCommunications Balanced system considerationsRS-485 maximum cable length RS-485 wiringRS-485 network configuration RS-485 cableEthernet communications Ethernet configurationEthernet wiring EthernetETHERNET SwitchSWITCH/ hub/ HUB Digital outputsStatus input connections Status inputsRelay outputs Digital output connectionsRelay output connections Heartbeat / communications LED Front panel display and meter setupLED indicators Alarm / energy pulsing LED modesNotification icons Meter screen menusRelated topics PM5300 display screen menus Menu treeBasic setup screen Front panel meter setupMeter setup screen navigation Configuring the basic setup parametersBasic setup menu tree Basic setup parametersParameter Values Description Communication ports Communications setupSetting up serial communications Serial communications setup menu treeSetting up Ethernet communications Communications setup parametersEthernet communications setup menu tree Display setup menu tree HMI settingsSetting up the display Ethernet port settingsRegional settings menu tree Setting up the screen passwordsSetting up regional settings Display setup parametersLost password Password setup menu treePassword setup parameters Advanced setup menu tree Setting the clock Advanced setupClock setup menu tree Clock setup parametersLED setup parameter Setting up the alarm / energy pulsing LEDAdvanced setup parameters Alarm / energy pulsing LED settings menu treeInput / output setup Demand setup Demand setup menu treePower or current demand setup parameters Multi-tariff setup Alarms setupRemote Meter Setup Displaying data screens Viewing Meter DataViewing meter data from the front panel Meter data display screensEnergy E Power PQSVolts U-V HarmMnMx AlarmHz F UnbalMaint Using ION Setup to view or modify configuration dataUsing software to view meter data TimerInput / Output Status input applicationsStatus Input, Digital Output Ports and Relay Output Ports Status input setup parameters available through ION Setup Status input setupConfiguring status inputs using ION Setup Navigate to I/O configuration I/O SetupStatus input setup menu tree Configuring status inputs using the front panelDigital output application example Digital output setupDigital output wiring example Digital output applicationsDigital output setup parameters available through ION Setup Configuring digital outputs using ION SetupDigital output setup menu tree Configuring digital outputs using the front panelOn Time s This defines the pulse width on time in seconds Parameter Values Description Relay output applications Relay output setupConfiguring relay outputs using ION Setup Relay output setup parameters available through ION SetupSet to External or Alarm. The relay output Relay output setup menu tree Configuring relay outputs using the front panel Alarm / energy pulsing LED setup Navigate to I/O configuration Energy Pulsing Disabled turns off the LED completely Alarms About AlarmsSecond Alarms Alarm List of Standard 1-Second Over/Under AlarmsHow the power meter handles setpoint-driven alarms Digital AlarmsUsing an Alarm to Control a Relay and Digital Output Alarm SetupUnary Alarms Alarm PrioritiesSetting Up 1-Second Alarms Setting Up 1-Second Alarms Setting Up Unary Alarms Setting Up Digital Alarms Setting Up Digital Alarms Viewing Active Alarms and Alarm Counters Viewing Alarm Activity and HistoryViewing Unacknowledged Alarms and the Alarm History Log PowerLogic PM5300 series user guide Alarms Data Logs Data LogsDescription Number of Registers Data Type Register Number Alarm Log Alarm Log StorageMemory Allocation for Log Files Energy Power factorMeasurements and calculations Real-time readingsPower factor minimum and maximum Power factor min/max conventionPower factor sign convention IEC modeBlock interval demand Power demand calculation methodsIeee mode DemandBlock interval demand example Synchronized demandThermal demand example Current demandPredicted demand Thermal demandPredicted demand example Peak demandMulti-tariff feature Multi-tariff feature exampleMulti-tariff feature overview Front panel date and time format Command mode overviewTime of day mode overview Time formatTariff Type Start date End date Start time End time Example tariff configurations for a four-tariff systemConfiguration 1 four tariffs with weekdays and weekends Tariff creation methodDigital input requirements for required number of tariffs Input mode overviewConfiguration 1 2 tariff assignment using 2 digital inputs1 Configuration 2 2 tariff assignment using 2 digital inputsTime of day mode tariff setup Configuring tariffs using the front panelConfiguring time of day mode tariffs using the front panel Tariff setup menu treeConfiguring input mode tariffs using the front panel Total Harmonic Distortion and Total Demand Distortion Power qualityHarmonic content calculations Harmonics overviewTDD calculation Viewing harmonics using the front panelDisplaying harmonics data THD and thd calculationsExample 13th to 21st harmonics for line-to-neutral voltage Viewing THD/thd using the front panelPower Quality display screen Viewing TDDRelated topics Testing overview Verifying accuracyAccuracy test requirements PM5300 Reference device or energy standardEnergy pulsing Location of energy pulsing LEDVerifying accuracy test Calculating total power Percent error calculationCalculating the number of required pulses VT and CT considerations Total power limit for alarm / energy LEDTotal power limit for digital output Energy pulsing considerationsVar-hour test points example Typical sources of test errorsTest points Watt-hour test points exampleReset menu tree Meter resetsFront panel meter reset screens Global resetsAlarm counter Option Description Single resetsSingle reset options Alarm counter optionsPowerLogic PM5300 series user guideChapter 13-Meter resets 102 Identifying the Firmware Version, Model, and Serial Number Maintenance and UpgradesPassword Recovery Power Meter MemoryMeter Control PowerAdditional Meter Status Information Downloading FirmwareTroubleshooting Heartbeat/Comms LED105 106 TroubleshootingPotential Problem Possible Cause Possible Solution Getting Technical Support Register ListMID compliance for the meter Specifications relevant to MIDMID Compliance MID overviewMID Compliance Installation and wiringLocation of terminal covers Installing the terminal coversPM5331/PM5341 default screen Default PM5331/PM5341 display screenMeter firmware version MID-protected setup parametersLock-protected setup parameters Lock-protected setup parametersInitializing the meter Setting up the PM5331/PM5341Setting up lock password Navigate to Maint Setup Meter LockLocking or unlocking the meter Glossary Terms113 114 115 Abbreviations116 117 118 Page Schneider Electric 35, rue Joseph Monier CS