Table 5-1. SPS 4001B Fault Finding

No calibration gas flow

Probable Cause

Recommended Corrective Action

Improper wire connections, loose

Properly connect wiring or secure loose wiring connections; replace damaged wiring if

connections, or damaged wiring

necessary.

 

 

Oxymitter 4000 logic I/O not set for calibration

Set logic I/O to mode 8 or 9 via HART/AMS.

handshaking with SPS 4001B

 

Clogged calibration gas line between tank and

Replace clogged calibration gas line.

manifold

 

Flow meter knob not turned counterclockwise

Turn calibration gas flow meter knob counter-clockwise to allow calibration gas to flow.

to allow flow

 

Clogged calibration gas line between manifold

Replace clogged calibration gas line.

and calibration gas flow meter

 

Blown fuse

Replace fuse per "Fuse Replacement", Section 4, Maintenance and Service

Circuit board not sending signals

Replace circuit board per "Circuit Board Replacement", Section 4, Maintenance and Service.

 

 

Clogged check valve

Replace check valve per "Check Valve Replacement", Section 4, Maintenance and Service.

Clogged calibration gas line between

Replace calibration gas line.

calibration gas flow meter and check valve

 

Clogged calibration gas flow meter

Replace calibration gas flow meter.

Solenoid failure

Replace solenoid per "Solenoid Replacement", Section 4, Maintenance and Service.

 

 

Pressure switch failure

Replace pressure switch per "Pressure Switch Replacement", Section 4, Maintenance and

 

Service.

 

 

5-3

Image 31
Contents SPS 4001B Single Probe Autocalibration Sequencer Page Table of Contents TOC-2 Essential Instructions SPS 4001B Single Probe Autocalibration SequencerPreface SymbolsDefinitions Component Checklist Description and SpecificationsOverview Specifications SpecificationsManifold Physical DescriptionCalibration Gas Flow Meter Pressure SwitchCalibration Gas Solenoids Circuit BoardTheory of Operation SPS 4001B Calibration Setup Overview Mechanical Installation Section InstallationReference Air Figure GAS ConnectionsCalibration Gas Figure Analytical Connections ElectricalGND SPS 4001B Overview Calibration Requirements Section OperationCalibration Gas Tanks Check Valve Liquid Carbonic GAS Corp Specialty GAS LaboratoriesTimed Interval CAL RecommendedSEMI-AUTOMATIC Calibration Fuse Replacement Maintenance and ServiceSPS 4001B, Exploded View Installation REMOVE/INSTALL ChassisRemoval Terminal Connections Solenoid Replacement Circuit Board ReplacementPressure Switch Replacement SPS 4001B Troubleshooting TroubleshootingRelay Failure SPS 4001B Fault Finding SPS 4001B Troubleshooting Flowchart Sheet 1 SPS 4001B Troubleshooting Flowchart Sheet 2 SPS 4001B Replacement Parts SPS 4001B Index No Part Number Description Calibration ComponentsSPS 4001B Appendix a Safety Data Safety Instructionsimportant Belangrijk Vigtigt SPS 4001B Tärkeää SPS 4001B Wichtig Importante Viktig SPS 4001B SPS 4001B Viktigt SPS 4001B Returning Material Appendix B Return of MaterialsSPS 4001B Index Index-2 Warranty IM-106-340AC-1, Rev .0 April SPS 4001B Serial no Order no