Samples for Grounding

There is two of samples for grounding below.

Using a grounding wire

Determine the size of an external ground wire according to Article 690.46, NEC2014.

(Equipment grounding conductors smaller than 6 AWG shall be protected from physical damage.)

A grounding conductor with insulation or bare (no insulation) may be used, provided the terminations are reliably available.

Grounding wire

AC junction box

Using listed EGC

• Use equipment grounding conductors approved by Article 250.118, NEC2014.

Bonding jumper

EGC

(ex. metal rack)

grounding wire

AC junction box

LG AC module includes DC cables in the module’s internal wiring, so no grounding is required for DC input.

For equipment grounding, LG AC Module uses an external grounding equipment conductor. AC cable does not provide a grounding conductor, grounding is provided only by the external connection to the module frame.

17

Image 17
Contents AC Module System Installation Instructions Revisions Table of ContentsImportant Safety Instructions SafetySafety Symbols FCC Guidelines Circuit SymbolsFor Micro inverter & Communication Gateway For Communication Gateway Indoor use onlyAdvantages of AC Module System IntroductionAC Module System Communication gatewayAC Module Before InstallationInspecting the Area of Installation Measuring AC Voltage of the Utility Inspecting Components of the AC ModuleWiring Diagram of AC Module System Mounting the AC module Installing the AC Junction Box and PV RackProduct Specification Fix AC module to the PV rack in the following order Mounting According to the Type of PV rack Trunk connector insertion Connecting AC Modules Trunk CableTrunk connector removal Trunk cable usage and maintenancePage Checking Accessory Checking the AccessoriesCable Usages According to AC Junction Box Locations Grounding Samples for Grounding Male transition cable Connect the general AC cables in the following order AC output single phase 240VACAC output three phase 208VAC merge type AC output three phase 208VAC split type Operation MaintenanceChecking Components of the Communication Gateway EnerBoxTM Communication GatewayLED status Troubleshooting Connecting to the Communication GatewayConfiguring the Installation App Checking installed AC modules LGElectronics Setting the grid configuration Checking conditions of installed AC modulesWebsite Setting System ConfigurationDiagram Details AccessoriesAC Module Product SpecificationsParameter Section Value Section 240VAC 208VACDimensions Internal Communication with AC module EnerBoxRange Clearing Time s Response to Abnormal ConditionsDedicated Cables Transporting and Storage WarrantyContact Disclaimer of Liability