Desa (V)T36NA installation manual Installation for vertical termination, Flat Ceiling Installation

Page 14

Venting Installation

instructions

Continued

installation for vertical termination

Note: Vertical restrictor must be installed in all vertical installations.

1.Determine the route your vertical venting will take. If ceiling joists, roof rafters or other framing will obstruct the venting system, consider an offset (see Figure 19) to avoid cut- ting load bearing members. Note: Pay special attention to these installation instructions for required clearances (air space) to combustibles when passing through ceilings, walls, roofs, enclosures, attic rafters, etc. Do not pack air spaces with insulation. Also note maximum vertical rise of the venting system and any maximum horizontal offset limitations.

2.Set the fireplace in desired location. Drop a plumb line down from the ceiling to the posi- tion of the fireplace exit flue. Mark the center point where the vent will penetrate the ceiling. Drill a small locating hole at this point.

Drop a plumb line from the inside of the roof to the locating hole in the ceiling. Mark the center point where the vent will penetrate the roof. Drill a small locating hole at this point.

Roof Flashing

Wall Strap

45° Elbow

Ceiling Firestop

Figure 19 - Offset with Wall Strap and 45°

Elbows

Flat Ceiling Installation

1. Cut a 10" square hole in the ceiling using the locating hole as a center point. The opening should be framed to 10" x 10" inside dimen- sions, as shown in Figure 9 on page 9 using framing lumber the same size as the ceiling joists. If the area above the ceiling is an insu- lated ceiling or attic space, nail firestop from the top side. This prevents loose insulation from falling into the required clearance space. If the area above the ceiling is a living space, install firestop below the framed hole. The firestop should be installed with no less than three nails per side (see Figure 20).

2. Assemble the desired lengths of pipe and elbows necessary to reach from the fireplace flue up through the firestop. Be sure all pipe and elbow connections are fully twist-locked (see Figure 8, page 9).

3. Cut a hole in the roof using the locating hole as a center point. (Cover any exposed open vent pipes before cutting hole in roof.) The 10" x 10" hole must be measured on the horizontal; actual length may be larger depending on the pitch of the roof. There must be a 1" clearance from the vent pipe to combustible materials. Frame the opening as shown in Figure 9, page 9.

4. Connect a section of pipe and extend up through the hole.

Note: If an offset is needed to avoid obstruc- tions, you must support the vent pipe every 3 feet. Use wall straps for this purpose (see Fig- ure 19). Whenever possible, use 45° elbows instead of 90° elbows. The 45° elbow offers less restriction to the flow of the flue gases and intake air.

If area above is an attic or insulated area, install firestop above framed hole.

If area above is a living space, install firestop below framed hole.

Figure 20 - Installing Firestop

14

www.desatech.com

111250-01E

Image 14
Contents What to do if YOU Smell GAS Table of Contents Safety InformationSafety Information Product Identification Product FeaturesLocal Codes High traffic areasThis fireplace does not require electricity to operate Pre-Installation PreparationLocation and space requirements Proper clearances must be maintainedFront Top of Standoffs Vent See venting ClearancesFraming and finishing Venting clearancesLocation of Termination Cap Balcony with Perpendicular Side WallVenting Installation Instructions Installation PrecautionsInstallation Planning Installing Horizontal Vent Cap Noncombustible Exterior Ground Floor Installation 32 minSnorkel Termination Installation Recommended Applications Corner ground floor installationHorizontal System Installation Using TWO 90 Elbows Connect a section of pipe and extend up through the hole Installation for vertical terminationFlat Ceiling Installation Twist-lock the vent cap onto the last section of vent pipe High Altitude Installation Vertical VentingDesa Terminations Desa Venting AccessoriesDesa Elbows Number DescriptionModel BK Installation Fireplace InstallationInstalling optional blower accessories Check GAS TypeModel BKT Installation Plug in blower power cord to duplex outletInstallation Items Needed Installing Gas Piping to Fireplace LocationBlower Wiring Diagram Connecting Fireplace to GAS Supply Checking GAS ConnectionsPressure Testing Fireplace Gas Connections Test Pressures Equal To or Less Than Psig 3.5 kPaOpen bottom louver and locate the switch Installing optional wall mount switch GWMS2Installing Remote Receiver Removing Louver Panels Cleaning Glass DoorRemoving/Replacing Glass Door Removing Glass DoorInstalling logs, lava rock and glowing embers Close top and bottom louversInstalling Log No Lighting Instructions For your safety Read before lightingOperating Fireplace To Turn OFF GAS To ApplianceOn/Off Series Models HRC100 and HRC101 Manual Lighting ProcedureOptional Hand-Held Remote OperationAuto Shutoff Feature Operating optional blower accessorySafety Features Operating optional GWMT1 Wall Mounted ThermostatInspecting Burners Cleaning MaintenancePilot Assembly Burner Flame PatternVenting system Pilot and burnersLogs Troubleshooting Observed Problem Possible Cause RemedyBurner orifice clogged Clean burner see Cleaning Is lit Mocouple to cool, causingProblem could be caused by Replace pilot assembly After pilot lights, keep gasOr shut off Service person Remote does not function When burner is litDirty or partially clogged 3. Clean burner see Cleaning Tery power is lowGas leak. See Warning Statement aboveTechnical Service Replacement PartsService Hints SpecificationsRolled Louver Trim kit Wall mounted on/off switch gwms2 Not ShownFace/Louver Panel kit Deflection hoodIllustrated Parts Breakdown Rear Refractory Brick Panel Left Refractory Brick PanelIllustrated Parts Breakdown 11102 111250-01E 111250-01E Limited Warranty DIRECT-VENT Fireplace Warranty InformationKeep this Warranty