5.Installation

All instructions must be carried out in the order described, to prevent personal injury or damage to machinery.

Always take great care when handling the knives since they are very sharp and can cause personal injury.

The granulator should be connected to the mains supply by an authorised electrician.

5.1Pre-start checks

Before the granulator is installed, the rust preventive should be carefully cleaned from the parts which are not painted or rustproof.

Check the knife clearance and tightening torque on the attachment bolts for the knives.

5.1.1 Two hours after first start

Check the knife clearance again and tightening torque of the attachment screws for knives; check the attachment screws for both the fixed and rotating knives.

5.2Opening and closing the hopper and screenbox

Screenbox:

The screenbox is held in place by a spring-loaded hoisting mechanism, which is manoeuvred using the bar (4). Release the screenbox by moving the bar until it is horisontal.

1.Pull out the granule bin (3). A safety switch on the back of the granulator is then activated, which breaks the current to prevent the machine from being started with the screenbox open.

2.Loosen the socket-head nut at the top of the clamping ring (1). Turn the granulator, by using the motor as a lever, to the position shown in the figure opposite. Simultaneously put your weight against the motor so that the granulator does not turn freely and damage the blower motor.

Contd.

0 5 - 1 5 - 9 6

7 9

8

Image 8
Contents Manual Contents Introduction Technical specifications DimensionsData Serial NumberFunctional description OverviewSafety system Safety regulations = WARNING! Risk of being cut or caught in the machineryInstallation Pre-start checksTwo hours after first start Opening and closing the hopper and screenboxElectrical connection HopperOperation and daily maintenance Starting and stoppingInspection Daily inspectionCleaning Trouble-shootingOr at least once every 300 hours If the granulator does not startChanging the fixed and rotating knives ServicingChanging the knives Assembling the rotating knives Assembling the upper fixed knifeSharpening the knives OverviewSharpening the fixed and rotating knives Fixed knivesRotating knives Assembling Disassembling/assembling the screwDisassembling Lubrication Spare parts list 1a 79, Diagram 1b 79, Table Pos Qty2 79, Knives, fixed and rotating Electrical scheme Layout Options 11.1.1 79, Air-veyor Pause/pulse relay when emptying with Air-veyor Delay time interval T2 the timeSetting the sensitivity Level control, capacitiveTransporting and storing Storing