TC2 204060 Series BattChg Owners Guide.book Page 29 Friday, July 8, 2011 11:44 AM
Installing Batteries
Three-Stage Charging
The
The charger will restart the charging cycle in the Bulk stage if the lowest battery voltage of the three banks drops below 12.5 V (12 Vdc chargers) or 25 V (24 Vdc chargers) for 15 minutes. After seven days, the charger will automatically restart charging in order to refresh the batteries.
Vbat = Vabs | lout < 10% lrating |
for 1 minute | for 1 minute |
Battery Voltage |
|
Vbat = Vgas | Vbat < 12.5 V |
for 1 minute | for 15 minutes |
Vgas voltage |
|
|
|
Charge |
|
|
|
start |
|
|
|
BULK | ABS | ABS | FLOAT |
CC | CV | ||
|
| ABS CV timeout | Time |
|
|
|
max 5 hrs
Start of |
|
|
| FLOAT timeout | |
|
|
| max 7 days | ||
charging cycle |
|
|
| ||
Total ABS timeout | |||||
| |||||
| max 8 hrs |
Figure 9 Three-Stage Charging Process
|
| 29 |
|
| |||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|