Maintenance
Periodic maintenance
Perform periodic inspections to ensure that the HP POD 20c continues to perform according to design parameters. During periodic inspections, pay special attention to electrical connections and wiring.
For more specific maintenance information, see the HP Performance Optimized Datacenter 20c Maintenance and Service Guide.
Sample HP POD 20c maintenance schedule
For detailed maintenance information and schedules, consult with HP services.
The following table is a sample maintenance schedule for an HP POD 20c. For more detailed maintenance information, see the HP Performance Optimized Datacenter 20c Maintenance and Service Guide.
Component to be inspected | Frequency |
|
|
Electrical connections and | Every 30 days |
|
|
Electrical connections and | Every 180 days |
Condensation and drainage system | Every 30 days |
Condensation and drainage system | Every 90 days |
Busway interconnects (tightened) | Every 180 days |
EPO system | Every 180 days |
For more information about the | |
and so on) | components, see the Operation |
| and Maintenance manual for |
| the HP Performance Optimized |
| Datacenter 20c. |
|
|
Maintenance 77