There are 2 categories for venting:

I.Venting with Flue Manifolds FOT-203 or FOT-204 - horizontal venting directly through the wall with no extensions.

II. Extended Venting - horizontal and vertical terminations with a maximum 33 feet and 3 elbows.

I.Venting with Flue Manifolds FOT-203 and FOT-204

The following flue manifold sizes are available:

Name

Kit No.

fits walls

Vent Kit A

FOT-203

4 1/3 - 9 1/2 inch

 

 

(110 - 240 mm)

Vent Kit B

FOT-204

9 1/2 - 15 3/4 inch

 

 

(240 - 400 mm)

 

 

 

Flue extensions are not authorized to be used with the FOT-203 and FOT-204 manifolds.

FOT-203 / FOT-204

Drilling Flue and Gas Supply Holes

Check for water and gas pipes as well as electric cables. Use the template supplied to mark the wall locations for the flue manifold and the gas supply. Drill the flue hole using a 3 1/2 inch (90 mm) drill.

For weatherboard walls, drill through the center of the weatherboard from the outside first and then through the plasterboard.

Flue Manifold Installation

1. Disassemble the Flue Manifold The flue consists of 3 parts:

sleeve

Inside Connection

Terminal

 

 

inside connection

terminal

Disassemble the flue manifold by first pulling

 

out the inside connection. To remove the

 

outer terminal pull and release the two

 

internal ties and then pull out the outer

 

terminal.

Sleeve

Clearance to combustibles for the sleeve and flanges is zero inches.

20

Rinnai Corporation RHFE-750ETRA

Image 20
Contents RHFE-750ETRA Table of Contents Safety Behavior and Practices Safety Features Specifications Natural Gas Propane GasFeatures DimensionsDescription Part Number Front PanelFront Panel Models Remote Control Features Remote Control CareRemote Control Operation Sequence of OperationsBasic Fireplace Operations Turning on and OFFAdjusting the Temperature Flame FunctionObstruction of Warm Air Discharge Lock FunctionTimers Programming the clock and timersUsing the Override Pre-heatCare and Maintenance MaintenanceFilters Visual Inspection of FlameCleaning Combustion Chamber Glass Care of ExteriorTroubleshooting Problem Possible Solutions or ExplanationCode Fault Remedy Fault CodesReplacement of Thermal Fuse Parts Included for Installation General InstructionsClearances to Combustibles Flue Terminal ClearancesSide clearances for air vents Clearances for a Mantle or Decorative OverhangDescription Canadian Installations US Installations Location 28.3 in 720 mmCorrect Floor Flue Manifold Installation VentingVenting with Flue Manifolds FOT-203 and FOT-204 Drilling Flue and Gas Supply Holes+ c II. Extended Venting Horizontal and Vertical Terminations Maximum Length = 33 feet 10 m and 3 elbows Manufacturer Metal-FabPart Description Number Vent Length Switch Additional Venting ClearancesConnections Mounting points Final Assembly Install the LogsCondensate Tray Install the Front Panel Air Guide VanesFor Your Safety Read Before Operating Operating InstructionsWiring and Schematic Diagrams Parts List Parts List 109 QTY Description Comments NG Left and Right Packing for AIR Inlet BOX Warranty Information Limited WarrantyWhat is covered? RHFE-750ETRA Direct Vent FireplaceLimitation on warranties How do I get service? What is not covered?What will Rinnai do? Issue G