Heatiator CD4236IR-C, CD4236ILR-C Vent Clearances and Framing, Pipe Clearances to Combustibles

Page 37

8 Vent Clearances and Framing

A. Pipe Clearances to Combustibles

WARNING! Risk of Fire! Maintain air space clearance to vent. DO NOT pack insulation or other combustibles:

Between ceiling firestops

Between wall shield firestops

Around vent system

Failure to keep insulation or other material away from vent pipe may cause over heating and fire.

Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).

DVP heat shield - designed to be used on a wall 4 in. to 7-1/4 in. (102 mm to 184 mm) thick.

If wall thickness is less than 4 in. the existing heat shields must be field trimmed. If wall thickness is greater than 7-1/4 in. a DVP-HSM-B will be required.

SLP heat shield - designed to be used on a wall 4-3/8 in. to 7-5/8 in. (111 mm to 194 mm thick).

If wall thickness is less than 4-3/8 the existing heat shields must be field trimmed. If wall thickness is greater than 7-5/8 in. a DVP-HSM-B will be required.

B. Wall Penetration Framing

Combustible Wall Penetration

Whenever a combustible wall is penetrated, you must frame a hole for the wall shield firestop(s). The wall shield firestop maintains minimum clearances and prevents cold air infiltration.

• The opening must be framed on all four sides using the

same size framing materials as those used in the wall

construction.

• SLP pipe - A wall shield firestop must be placed on each

side of an interior wall. A minimum 1-1/2 in. (38 mm)

overlap of attached heat shields must be maintained.

• DVP pipe - A wall shield firestop is required on one side

only on interior walls. If your local inspector requires a

wall shield firestop on both sides, then both wall shield

firestops must have a heat shield (refer to Section 16.B.)

attached to them.

3 in. (76 mm) top clearance

1 in. (25 mm) clearance around vertical sections

(DVP-SLP Pipe Shown)

Heat

3 in. (76 mm)

Shield

top clearance *

 

Heat

 

Shield

 

1 in. (25 mm)

Wall

clearance

Shield

bottom & sides

Firestop

 

 

WALL

• See Section 10.L. for information for regarding the in-

stallation of a horizontal termination cap.

Non-Combustible Wall Penetration

If the hole being penetrated is surrounded by noncom- bustible materials such as concrete, a hole with diameter one inch greater than the pipe is acceptable.

Whenever a non-combustible wall is penetrated, the wall shield firestop is only required on one side and no heat shield is necessary.

Heat

Shield

Wall

Shield

Firestop

WALL

3 in. (76 mm) top clearance *

Heat

Shield

1 in. (25 mm) clearance bottom & sides

10 in. 12 in.

10 in.

12 in.

C

D

*When using SLP or SL-D pipe, minimum clearances from the vent pipe to combus- tible materials at inside wall firestops are: Top: 2-1/2 in. (64 mm)

Bottom: 1/2 in. (13 mm)

Sides: 1 in. (25 mm)

Figure 8.1 Horizontal Venting Clearances To Combustible Materials

A* B*

 

 

A*

B*

C

D

CD4236

in.

42-3/4

27-7/8

41-3/4

26-7/8

mm

1086

708

1060

683

 

CD4842

in.

44-3/4

29-7/8

44-1/8

28-7/8

mm

1137

759

1111

733

 

*Shows center of vent framing hole for top or rear venting. The center of the hole is one (1) in. (25.4 mm) above the center of the horizontal vent pipe.

Figure 8.2 Wall Penetration

Heatilator • CD4236IR-C, CD4842IR-C2207-900 Rev. J • 11/11

37

Image 37
Contents What to do if you smell gas Models CD4236IR-C CD4842IR-C CD4236ILR-C CD4842ILR-CHOT Surfaces Hot glass will cause burnsHomeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Remote Controls, Wall Controls and Wall Switches Fixed Glass AssemblyIPI Battery Tray/Battery Installation Fan Kit optionalNine Hour Safety Shutdown Feature Module ResetControl Module Operation Before Lighting FireplaceFinal inspection by Lighting Instructions IPIWhat to do if YOU Smell GAS GAS ValveIssue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Maintenance and Service Gasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianLogs FireboxExtra Screws to be Removed for CD4842IR-C Logs/Grate and Valve Assembly RemovalRemove burner skirt by removing 4 screws. See Figure 12 Burner identification Examples Burner Identification/VerificationTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Any such action may cause a fire hazardSelecting Appliance Location Framing and ClearancesCD4236 Series CD4842 SeriesConstructing the Appliance Chase Minimum Framing DimensionsMantel and Wall Projections ClearancesVent Termination Minimum Clearances Termination LocationsInches U.S.A Covered Alcove ApplicationsApproved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsTop Vent Horizontal Termination Vent DiagramsTwo Elbows Top Vent Horizontal Termination One ElbowV1 Minimum H1 Maximum V1 Minimum H1 + H2 MaximumMin Max Top Vent Horizontal Termination Three ElbowsBreak Here Maximum + V 2 Min Top Vent Vertical TerminationH1 + H2 V1 + V2 Minimum H1 + H2 Maximum Top Vent Vertical Termination Three ElbowsHeatilator CD4236IR-C, CD4842IR-C 2207-900 Rev. J 11/11 H1 Maximum V1 Minimum H1 + H2 Maximum Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Max Minimum Maximum Rear Vent Vertical Termination One Elbow Two ElbowsV1 Minimum H1 + H2 + H3 Maximum 10 ft Rear Vent Vertical Termination Three ElbowsPipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe DVP SLP Install the Ceiling FirestopInstalling the Optional Heat-ZoneGas Kit Install Attic Insulation ShieldFlat Ceiling Installation Vaulted Ceiling InstallationTop Vent Appliance PreparationCut the metal retaining band and fold the sides out Rear VentSecuring and Leveling the Appliance Installing the Non-combustible BoardHeader Attach Vent to the Firebox Assembly Installing Vent Pipe DVP and SLP PipeAssemble Vent Sections DVP Pipe Only Assemble Pipe SectionsAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingInstall Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination DVP-HPC1 DVP-HPC2 Install Horizontal Termination Cap DVP and SLP PipeFuel Conversion Gas InformationGas Pressure Gas ConnectionIntelliFire PlusTM Ignition System Wiring Wiring RequirementsOptional Accessories Requirements Electrical InformationWall Switch Installation for Fan Optional Electrical Service and Repair Junction Box InstallationFacing Material FinishingCombustible Mantels CD4236Appliance Setup Install the Log Assembly LOG Placement InstructionsAir Shutter Setting Install Trim and/or SurroundAir Shutter Settings CD4236IR-C CD4842IR-C Fully OpenSymptom Possible Cause Corrective Action TroubleshootingIntelliFire PlusTM Ignition System Troubleshooting Reference Materials Appliance Dimension DiagramLocation Inches Millimeters GAS Line Access R Left Side TOP View Front View Right View DVP-AS2 Vent Components DiagramsHorizontal Termination Cap DVP-TRAPBEK DVP-BEK2 RF6M RF12MDVP-TRAPFL COOL-ADDDVP-FBHT PVI-SLP Optional Wire HarnessSLP-LPC DVP-HRC-SS DVP-HRC-ZC-SSElbow 222 mm 165 mm 165 mm9-1/4 235 mm 152 mm 168 mm251 mm Effective Height LengthSLP-SNKD SLP-CCS-BK SLP-TVHW SLP-HRC-SS SLP-HRC-ZC-SS Fire RiskLog Set Assembly Service PartsAt Depot 36 in. Caliber DV42 in. Caliber DV StockedCD4236IR-C #19 Valve AssemblyCD4842IR-C Beginning Manufacturing Date Dec Ending Manufacturing DateCD4236IR-C, CD4236ILR-C, CD4842IR-C, CD4842ILR-C Contact Information