Quadra-Fire CASTILE-GAS-CSB, CASTILE-GAS-MBK, 7023-111E, CASTILE-GAS-PMH owner manual 203mm

Page 13

Step 3.

For installations using a round support box/wall thimble (check pipe manufacturer's instructions), mark the wall for a 10 in. x 10 in. (254mm x 254mm) square hole. The center of the square hole should line up with the center line of the horizontal pipe, as shown in Figure 5.5. Cut and frame the hole in the exterior wall where the vent will be terminated. If the wall being penetrated is constructed of noncombustible material, i.e. masonry block or concrete, a 7 in. (178mm) diameter hole is acceptable.

Center of Hole

Center Line

 

 

Wall

 

 

Center Line

 

 

 

 

 

 

 

 

Thimble

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 5.5

NOTE:

(1)Installation requires a minimum of 6 in. (152mm) horizontal run of vent with a 1/4 in. (6mm) rise run towards the termination. Each 1 ft. (305mm) of horizontal venting must include a 1/4 in. (6mm) rise. Never allow the vent to run downward. This could cause high temperatures and may present the possibility of a house or structure fire.

(2)The location of the horizontal vent termination on an exterior wall must meet all local and national building codes, and must not be easily blocked or obstructed, see Figure 4.4 on page 9.

(3)For installations requiring a vertical rise on the exterior of the building, a snorkel kit is available with a 14 in. (356mm) and a 36 in. (914mm) tall snorkel termination cap. Follow the same installation procedures as used for standard horizontal terminations. If the snorkel termination must be installed below grade (i.e. basement application), proper drainage must be provided to prevent water from entering the snorkel termination. Do not backfill around snorkel termination.

(4)Vertical clearances through a wall require 2 in. (51mm) off the top of the venting pipe and 1 in. (25mm) off the sides and bottom.

Step 4.

Position the horizontal termination cap in the center of the 10 in. x 10 in. (254mm x 254mm) square hole and run a bead of non-hardening mastic around its outside edges, so as to make a seal between it and the wall, attach termination cap to the exterior wall with the four wood screws provided. The arrow on the vent cap should be pointing up (Figure 5.6).

Wood

Screw

HOT

Wall Thimble

Figure 5.6

NOTES:

(1)The four wood screws provided should be replaced with appropriate fasteners for stucco, brick, concrete, or other types of sidings.

(2)A termination cap with a built-in vinyl siding standoff is highly recommended on a building with vinyl siding. The pilot hole will be 2 in. (51mm) closer to the bottom of the square than the top. Using a framing square, draw a 14 in. x 14 in. (356mm x 356mm) square around the pilot hole in the siding. See Figure 5.7.

8 in.

 

(203mm)

 

 

7 in.

 

(178mm)

7 in.

6 in.

(178mm)

 

(152mm)

Figure 5.7

July 29, 2008

Quadra-Fire · Castile Gas Stove · 7023-111E

Page 13

Image 13
Contents Do not Discard this Manual What to do if you smell gasDo Discardnot Hot glass will cause burnsWelcome to the Quadra-Fire Family Table of Contents 1Listing and Code Approvals BELOW. Keep Clear of ALL Obstructions Requirements for the Commonwealth of MassachusettsManufacturer Requirements Tools will apply to every installation Design & Installation ConsiderationsGetting Started Inspect Appliance & ComponentsClearances Selecting Appliance LocationVent Termination Minimum Clearances 4Termination LocationsAlcove Applications Venting Components Vent InformationUse of Elbows Measuring StandardsExceptions for Horizontal Installations How to Use the Vent Graph Venting GuidelinesType B Straight Out Installation Type a Up and Out InstallationType C 45 Elbow in Corner Installation Horizontal Termination203mm Step Direct Vent Pipe Vertical TerminationStep Twist-lock the vent cap and seal Cathedral Ceiling Class a Metal Chimney Type a & B Co-Axial to Co-Linear Type C Up & Out InstallationExisting Masonry Chimney Type a Type BCut and bend flashing as needed to fit Sealant adhesive Retro Connector Fuel Conversions Gas InformationConverting to LP Gas Propane Natural GASScrews Rubber Gasket Identification Label F Valve Regulator ReplacementPressure Gas Pressures Gas ConnectionCheck for GAS Leaks Connecting to the Appliance Recommendation for WireStanding Pilot Ignition System Wiring Wire Size Max. LengthON/OFF Accessories Appliance SetupRemove Shipping Materials Top to Rear Vent ConversionLeg Leveling System Baf e Installation/AdjustmentMineral Wool Positioning the LogsOpening Front Door 16 nut Snap disc through bracket Glass Door Assembly Blower InstallationBlower Shutter Adjustment Damper Adjustment For top or rear vent installationsBefore Lighting Appliance Operating InstructionsControls Lighting Appliance For Your Safety Read Before LightingInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit Symptom Possible Cause Corrective Action TroubleshootingBe Placed in this Opening After servicing Maintaining and Servicing Your ApplianceNecessary. USE Caution When CLEANING/HANDLING Ceramic Burner Maintenance Tasks InspectReference Materials Appliance Dimension DiagramSL-D Series Vent Components Vent Components DiagramHHT SL-P Vent Components ListTermination Caps & Kits Castile GAS Nbr Description Service Parts List cont’d. Castile GASSKU Part DescriptionAlphabetical Order RV-CG-MBK Accessories Warranty Policy Lifetime WarrantyContact Information Castile GasDealer Telephone