Quadra-Fire 7023-111E, CASTILE-GAS-MBK, CASTILE-GAS-CSB, CASTILE-GAS-PMH Cathedral Ceiling

Page 18

2. Cathedral Ceiling

Step 1.

Follow installation Steps 1 and 2 under vertical installation section, page 15.

Step 2.

Using the plumb-bob, mark the center line of the venting system on the ceiling, and drill a small hole through the ceiling and roof at this point. From the roof, locate the drill hole and mark the outline of the cathedral ceiling support box.

Step 3.

Remove shingles or other roof covering as necessary to cut the rectangular hole for the support box. Cut the hole 1/8 in. (3mm) larger than the support box outline.

Step 4.

Lower the support box through the hole in the roof until the bottom of the support box protrudes at least 2 in. (51mm) below the ceiling (Figure 5.17). Align the support box both vertically and horizontally with a level. Temporarily tack the support box in place through the inside walls and into the roof sheathing.

Level

Cathedral Ceiling

Support Box

2 in. (51mm) Min. below finished ceiling

Cut hole 1/8 in. (3mm) greater in size than pattern of support box as it is projected onto roof line

Figure 5.17

Step 5.

Using tin snips, cut the support box from the top corners down to the roofline, and fold the resulting flaps over the roof sheathing (Figure 5.18). Before nailing it to the roof, run a bead of non-hardening mastic around the top edges of the support box to make a seal between it and the roof. Clean out any combustible material from inside the support box.

Figure 5.17

Step 6.

Complete the cathedral ceiling installation by following the same procedures outlined in steps 4 through 8 for vertical installations, pages 16-17.

Step 7.

Place the support clamp (provided with the support box) inside the support box (at the bottom), and secure to the pipe section. The clamp allows the support box to support the weight of the pipe sections. Continue to add pipe sections until you are above the roofline.

Step 8.

Install the black trim collar around the outside of the cathedral ceiling support box (Figure 5.19). The two pieces of the trim collar slide over one another to allow for easy adjustment around the support box. Using the six screws provided, secure the four corners and the overlapping sections of the trim collar to the ceiling. You may want to predrill the holes for the overlapped sections for ease of installation.

Trim Collar

Cathedral

Ceiling

Support Screws

Box

Figure 5.19

Page 18

Quadra-Fire · Castile Gas Stove · 7023-111E

July 29, 2008

Image 18
Contents Do Discardnot What to do if you smell gasDo not Discard this Manual Hot glass will cause burnsWelcome to the Quadra-Fire Family Table of Contents 1Listing and Code Approvals Requirements for the Commonwealth of Massachusetts BELOW. Keep Clear of ALL ObstructionsManufacturer Requirements Getting Started Design & Installation ConsiderationsTools will apply to every installation Inspect Appliance & ComponentsSelecting Appliance Location Clearances4Termination Locations Vent Termination Minimum ClearancesAlcove Applications Use of Elbows Vent InformationVenting Components Measuring StandardsHow to Use the Vent Graph Venting Guidelines Exceptions for Horizontal InstallationsType C 45 Elbow in Corner Installation Type a Up and Out InstallationType B Straight Out Installation Horizontal Termination203mm Step Vertical Termination Direct Vent PipeStep Twist-lock the vent cap and seal Cathedral Ceiling Class a Metal Chimney Existing Masonry Chimney Type a Type C Up & Out InstallationType a & B Co-Axial to Co-Linear Type BCut and bend flashing as needed to fit Sealant adhesive Retro Connector Converting to LP Gas Gas InformationFuel Conversions Propane Natural GASValve Regulator Replacement Screws Rubber Gasket Identification Label FGas Pressures Gas Connection PressureCheck for GAS Leaks Standing Pilot Ignition System Wiring Recommendation for WireConnecting to the Appliance Wire Size Max. LengthON/OFF Remove Shipping Materials Appliance SetupAccessories Top to Rear Vent ConversionBaf e Installation/Adjustment Leg Leveling SystemPositioning the Logs Mineral WoolOpening Front Door Glass Door Assembly Blower Installation 16 nut Snap disc through bracketBlower Damper Adjustment For top or rear vent installations Shutter AdjustmentOperating Instructions Before Lighting ApplianceControls For Your Safety Read Before Lighting Lighting ApplianceFrequently Asked Questions Initial Break-in ProcedureAfter Appliance is Lit Troubleshooting Symptom Possible Cause Corrective ActionBe Placed in this Opening Maintaining and Servicing Your Appliance After servicingMaintenance Tasks Inspect Necessary. USE Caution When CLEANING/HANDLING Ceramic BurnerAppliance Dimension Diagram Reference MaterialsVent Components Diagram SL-D Series Vent ComponentsVent Components List HHT SL-PTermination Caps & Kits Castile GAS Service Parts List cont’d. Castile GAS Nbr DescriptionPart Description SKUAlphabetical Order RV-CG-MBK Accessories Lifetime Warranty Warranty PolicyCastile Gas Contact InformationDealer Telephone