Step 3.

To install the round support box/wall thimble cover in a flat ceiling, cut a 10 in. (254mm) square hole in the ceiling, centered on the hole drilled in Step 2. Frame the hole as shown in Figure 5.13.

Ceiling

Joists

Framing

Figure 5.13

1 - 1/2 in. (38mm) Long

Wood Screws

 

Step 4.

Assemble the desired lengths of pipe and elbows necessary to reach from the appliance up through the round support box. Ensure that all pipe and elbow connections are in their fully twist-locked position. Assemble as instructed.

Step 5.

Cut a hole in the roof centered on the small drill hole placed in the roof in Step 2. The hole should be of sufficient size to meet the minimum requirements for clearance to combustibles, as specified. Continue to assemble lengths of pipe and elbows necessary to reach from the ceiling support box/wall thimble up through the roof line. Galvanized pipe and elbows may be utilized in the attic, as well as above the roofline. The galvanized finish is desirable above the roofline, due to its higher corrosion resistance.

NOTE:

(1) If an offset is necessary in the attic to avoid obstructions, it is important to support the vent pipe every 3 ft. (914mm) to avoid excessive stress on the elbows, and possible separation. Wall straps are available for this purpose, Figure 5.12, page 15.

(2)Whenever possible, use 45° elbows, instead of 90° elbows. The 45° elbow offers less restriction to the flow of flue gases and intake air.

Step 6.

Slip the flashing over the pipe section(s) protruding through the roof. Secure the base of the flashing to the roof with roofing nails. Ensure the roofing material overlaps the top edge of the flashing as shown in Figure 5.14. Verify that the chimney is the required height above the roof. See roof pitch table, Figure 4.3, on page 8.

Shingles overlap on

CAP AND STORM

COLLAR NOT SHOWN

top edge of flashing

FOR CLARITY

 

Figure 5.14

Step 7.

Continue to assemble pipe sections until the height of the vent (before adding the termination cap) meets the minimum code requirements as outlined in the current CAN/CGA- B149 Installation Codes (in Canada), the National Fuel Gas Code NFPA 54/ANSI Z223.1 (in USA), or local codes. Note that for steep roof pitches, the vent height must be increased. See Roof Pitch Table (Figure 4.3, on page 8). In high wind conditions, nearby trees adjoining rooflines, steep pitched roofs, and other similar factors can result in poor draft, or down drafting. In these cases increasing the vent height or switching to the high wind termination cap may solve this problem.

Step 8.

Slip the storm collar over the pipe, and push it down to the top of the flashing (Figure 5.15). Use non-hardening sealant above and below the joint between the storm collar and the pipe.

Optional High Wind Termination Cap

Secure Flashing with Non-Hardening

Sealant and Roofing Nails

Figure 5.15

16

Quadra-Fire • Topaz • 7009-113 Rev. J • 12/11

Image 16
Contents Do Discardnot Hot glass will cause burnsWelcome to the Quadra-Fire Family Table of Contents 1Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Manufacturer RequirementsGas Equipment Venting System Provided Gas Equipment Venting System not ProvidedDesign & Installation Considerations Getting StartedInspect Appliance & Components Tools and Supplies NeededClearances Selecting Appliance LocationDesign Purposes only 4Termination Locations Vent Termination Minimum ClearancesAlcove Applications Vent Information Venting ComponentsUse of Elbows Measuring StandardsHow to Use the Vent Graph Venting GuidelinesVertical Distance From Appliance toType a Up & Out Installations for Top Vent Configurations Type B Rear Installations for Use with Rear Vent KitHorizontal Termination StepTop Vent Touching the hot cap Direct Vent Pipe Vertical TerminationStep Ceiling Joists Framing 2 in mm Long Wood Screws Twist-lock the vent cap and seal Cathedral Ceiling Class a Metal Chimney Existing Masonry Chimney Fire Risk Explosion Risk Retro Connector Fuel Conversions Gas InformationConverting to LP Gas Valve Regulator Replacement Propane Natural GASGas Pressures PressureGas Connection Check for GAS LeaksRecommendation for Wire Connecting to the ApplianceStanding Pilot Ignition System Wiring Wire Size Max. LengthSwitch Red 28 Thermocouple Gas Pilot Ignitor ThermopileIgnitor Red 28 711mm ON/OFFRemove Shipping Materials Appliance SetupTop to Rear Vent Conversion Accessories Leg Leveling SystemBrick Installation Front Installation Fronts shipped attached to faceFor Both Quartet and Solitaire Fronts Positioning the Logs Qty DescriptionMineral Wool Glass Door Assembly Replacement Blower InstallationWhite Damper Adjustment Shutter AdjustmentFor TOP or Rear Vent Installations Make adjustmentBefore Lighting Appliance Operating InstructionsControls For Your Safety Read Before Lighting Lighting ApplianceInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit Troubleshooting Symptom Possible Cause Corrective ActionBe Placed in this Opening Maintaining and Servicing Your Appliance After servicingMaintenance Tasks Inspect Necessary. USE Caution When CLEANING/HANDLING Ceramic BurnerAppliance Dimension Diagram Reference MaterialsVent Components Diagram Mm inner pipe 6-5/8 in mm outer pipeVent Components List DescriptionSimpson Dura-VentHHT SLP SimpsonDescription Dura-Vent Termination Caps & KitsLog Set Assembly Part number list on following RD. Service Parts ListDirect Vent Gas Stove Service Parts List StockedAt Depot Description Comments Part NumberSIDE-TPZ-MBK BRNR-TOPAZSIDE-TPZ-POR TOUCHUP-CSB TOUCHUP-CWLStocked Description Comments Part Number Accessories BK-GASWSLG-CSB FastenersLimited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Contact Information TopazDealer Telephone